US Lawyer Database

For Lawyer-Seekers

YOU DESERVE THE BEST LAWYER

Home » US Law » 2021 Kansas Statutes » Chapter 16 - Contracts And Promises » Article 19 - Kansas Fairness In Public Construction Contract Act » 16-1907 Provisions waiving right to collect damages for delays, void, unenforceable.

16-1907. Provisions waiving right to collect damages for delays, void, unenforceable.
Any provision in a contract that purports to waive the rights of a party to the contract to collect damages for delays caused by another party to the contract shall be void, unenforceable and against public policy. This provision is not intended to create a contract between parties where a contract did not otherwise exist.

History: L. 2007, ch. 163, § 7; July 1.