Home » US Law » 2022 West Virginia Code » Chapter 22. Environmental Resources » Article 21. Coalbed Methane Wells and Units » §22-21-17. Review of Application; Hearing; Pooling Order; Spacing; Operator; Elections; Working Interests, Royalty Interests, Carried Interests, Escrow Account for Conflicting Claims, Division Order

(a) Prior to the time fixed for a hearing under subsection (b) of this section, the board shall also set a time and place for a conference between the proposed applicant to operate a coalbed methane drilling unit and all persons to whom notice has been given under subsection (a), section sixteen of this article who have not entered into a voluntary agreement. At such conference the applicant and such other persons present or represented having an interest in the proposed unit shall be given an opportunity to enter into voluntary agreements for the development of the unit upon reasonable terms and conditions.

No order may be issued by the board as to any unit unless the applicant submits at the hearing a verified statement setting forth the results of the conference. If agreement is reached with all parties to the conference, the board shall find the unit is a voluntary unit and issue an order consistent with such finding.

(b) The review board shall, upon request of a proposed applicant for a drilling unit or upon request of a coal owner or operator, provide a convenient date and time for a hearing on the application for a drilling unit, which hearing date shall be no sooner than thirty-five days nor more than sixty days of the date the request for hearing is made. The review board shall review the application and on the date specified for a hearing shall conduct a public hearing. The review board shall take evidence, making a record thereof and consider:

(1) The area which may be drained efficiently and economically by the proposed coalbed methane well or wells;