(a) Upon the receipt of a complete surface-mining application or significant revision or renewal thereof, including public notification and an opportunity for a public hearing, the director shall grant, require revision of, or deny the application for a permit within sixty days and notify the applicant in writing of the decision. The applicant for a permit, or revision of a permit, has the burden of establishing that the application is in compliance with all the requirements of this article and the rules promulgated hereunder.
(b) No permit or significant revision of a permit may be approved unless the applicant affirmatively demonstrates and the director finds in writing on the basis of the information set forth in the application or from information otherwise available which shall be documented in the approval and made available to the applicant that:
(1) The permit application is accurate and complete and that all the requirements of this article and rules thereunder have been complied with;