§ 695. Marking Underground Facilities; noncompliance with requirement; records

(a) Any Operator of a Underground Facility who receives timely notification of any Proposed Excavation Work in accordance with section 694 of this chapter shall, within 2 business days after that notification, or before the indicated start of the excavation work, whichever is later, or at a later time mutually agreeable to the Operator and […]

§ 696. Excavating near underground facilities

When excavating within the Tolerance Zone, the excavator shall do all of the following: (1) Plan the excavation to avoid damage to. or minimize interference with the underground facilities in and near the construction area; (2) Determine the exact location of any marked Underground Facility using non-invasive methods of excavation. Methods to consider include hand […]

§ 697. Project engineer’s responsibility; design requests

(a) Any person may submit a Design Locate Request to the Notification Center. The Design Locate Request must: (1) Describe the tract or parcel of land for which the Design Locale Request has been submitted, with sufficient particularity, as defined by policies developed and promulgated by the Notification Center, to enable the facility Operator to […]

§ 691. Short title

This chapter may be cited as “The Underground Facility Damage Prevention and Safety Act.”

§ 691a. Legislative intent

The Legislature declares it to be the policy of the Government of the Virgin Islands and the purpose of this chapter to aid the public by preventing injury to persons and property and preventing the interruption of services resulting from damage to an Underground Facility caused by excavation or demolition operations and to provide minimum […]

§ 691b. Definitions

As used in this chapter, unless the context clearly indicates otherwise: (a) “Tolerance Zone” means a strip of land not less than 18 inches on either side measured on a horizontal plane and from the outer edge of the exterior surface of the underground facility. (b) “Business Days” means any day other than business days, […]

§ 692. Notification Center Structure

(a) There is established within the Department of Public Works a single, comprehensive territorial one-call Notification Center to provide notice of all excavations or demolitions near Underground Facilities. (b) All Operators, as defined in this chapter, shall participate in and share in the costs of the territorial Notification Center established under this section of this […]