US Lawyer Database

§ 19-11-1401. Title

This subchapter shall be known and may be cited as the “Construction Manager-General Contractor Method of Procurement Pilot Program”.

§ 19-11-1402. Legislative findings

The General Assembly finds that: (1) An efficient transportation system is critical for Arkansas’s economy and the quality of life of the state’s residents; (2) Transportation projects are costly and the revenues currently available for highways and local roads are inadequate to preserve and maintain existing infrastructure and to provide funds for highway improvements; (3) […]

§ 19-11-1403. Definitions

As used in this subchapter: (1) “Authorized contingency” means a provision prepared and submitted by the construction manager-general contractor as part of the guaranteed maximum price that is designed to cover costs that may result from: (A) Incomplete design; (B) Unforeseen and unpredictable conditions; or (C) Uncertainties within the defined transportation project scope that a […]

§ 19-11-1405. Project selection

If the Arkansas Department of Transportation determines that a construction manager-general contractor method of procurement is appropriate for a transportation project, the department shall establish a procedure for awarding the contract for construction of the construction manager-general contractor method transportation project using the criteria listed in § 19-11-1406.

§ 19-11-1202. Definitions

As used in this subchapter: (1) (A) “Energy cost savings measure” means: (i) A new facility that is designed to reduce the consumption of energy or natural resources or operating costs as a result of changes that: (a) Do not degrade the level of service or working conditions; (b) Are measurable and verifiable under the […]

§ 19-11-1406. Request for proposals

(a) A request for proposals under this subchapter shall include without limitation the following: (1) The minimum qualifications of the construction manager-general contractor; (2) The procedures for submitting a proposal to the Arkansas Department of Transportation, the criteria for the evaluation of and selection of a construction manager-general contractor to perform preconstruction services, and the […]

§ 19-11-1203. Energy cost savings measures authorized

(a) (1) A state agency may enter into a guaranteed energy cost savings contract in order to reduce energy consumption or operating costs of government facilities in accordance with this subchapter. (2) A state agency or several state agencies together may enter into an installment payment contract or lease purchase agreement with a qualified provider […]

§ 19-11-1407. Construction manager-general contractor selection

(a) The Arkansas Department of Transportation shall: (1) Prepare contract plans, specifications, special provisions, and other requirements composing the contract for construction of a transportation project elected for procurement using the construction manager-general contract method authorized by this subchapter; (2) Prepare a detailed construction cost estimate to evaluate the appropriate price for the construction of […]

§ 19-11-1204. Method of solicitation

Any solicitation of a guaranteed energy cost savings contract by a state agency shall be consistent with the Arkansas Procurement Law, § 19-11-201 et seq.