§ 22-10-202. Request by responsible public entity — Fees — Notice

(a) A responsible public entity may issue a request for proposals or invitation for bids from private entities for the development of a qualifying project using the guidelines adopted under this chapter. (b) The responsible public entity may charge a reasonable, nonrefundable fee to cover the costs of processing, reviewing, and evaluating a proposal or […]

§ 22-10-203. Requirements for proposals

(a) A qualifying project shall be developed only after the responsible public entity has issued a request for proposals or invitation for bids under § 22-10-202(a). (b) (1) A private entity that intends to be considered for a qualifying project under subsection (a) of this section shall submit a proposal or bid to the responsible […]

§ 22-10-204. Requirements for qualifying projects

(a) A responsible public entity may issue a request for proposals or an invitation for bids for the development of a qualifying project if the responsible public entity determines that: (1) There is a public need for or benefit to be derived from the type of qualifying project being proposed; (2) The proposals or bids […]

§ 22-10-301. Procurement requirements

(a) (1) A responsible public entity may enter into a comprehensive agreement only in accordance with this chapter. (2) A comprehensive agreement may include terms and conditions related to the procurement of services or materials related to the qualifying project. (b) In selecting a qualified respondent: (1) Sections 19-11-801 et seq. apply; (2) Competitive bidding […]

§ 22-10-302. Interim agreement

(a) Except as otherwise provided in this section, after a responsible public entity has selected the qualified respondent to a request for proposals or invitation for bids, the responsible public entity and the qualified respondent may negotiate an interim agreement that complies with the rules promulgated under this chapter. (b) A responsible public entity may […]

§ 22-10-303. Comprehensive agreement

(a) If a responsible public entity and the qualified respondent have entered into an interim agreement, agree on the findings and conclusions stated in the interim agreement, and desire to proceed with the development of the qualifying project, the responsible public entity and qualified respondent shall negotiate and enter into a comprehensive agreement. (b) If […]

§ 22-10-304. Financing of qualifying project

(a) (1) Financing of a qualifying project may be in the amounts and upon the terms and conditions stated in the interim agreement or the comprehensive agreement. (2) (A) A qualifying project may be financed by the qualified respondent or the responsible public entity, or both, and the qualified respondent and the responsible public entity […]

§ 22-10-101. Title

This chapter shall be known and may be cited as the “Partnership for Public Facilities and Infrastructure Act”.

§ 22-10-102. Legislative findings — Purpose

The General Assembly finds that: (1) There is a public need for the timely acquisition, design, construction, improvement, renovation, expansion, equipping, maintenance, operation, implementation, and installation of public infrastructure and government facilities within the state that serve a public purpose; (2) The public need for government facilities and public infrastructure may not be satisfied by […]

§ 22-10-103. Definitions

As used in this chapter: (1) “Affected local jurisdiction” means: (A) A county, a city of the first class, a city of the second class, an incorporated town, or a school district in which all or a portion of a qualifying project is located; and (B) Any other local governmental entity that is directly impacted […]