Section 701.565 – Notice of defect requirement; contents; mailing.

(1) Except as provided in ORS 701.600, an owner may not compel arbitration or commence a court action against a contractor, subcontractor or supplier to assert a claim arising out of or related to any defect in the construction, alteration or repair of a residence or in any system, component or material incorporated into a […]

Section 701.990 – Criminal penalties.

(1) Violation of ORS 701.021 is a Class A misdemeanor. (2) The intentional use of a contractor’s license number without the authorization of the licensed contractor is a Class A misdemeanor. (3) Use of a contractor’s license number, with or without the authorization of the licensed contractor, with the intent to deceive the public is […]

Section 701.992 – Civil penalties and other sanctions; enforcement.

(1) Except as provided in subsections (4) and (5) of this section, any person who violates any provision of this chapter or any rule adopted by the Construction Contractors Board shall forfeit and pay into the General Fund of the State Treasury a civil penalty in an amount determined by the board of not more […]

Section 701.580 – Offer by contractor, subcontractor or supplier; effect of accepting offer; nonperformance; compelling arbitration or commencing court action; admissibility of response or reply.

(1) An owner may accept an offer contained in a written response under ORS 701.570 by delivering a written acceptance to the offering contractor, subcontractor or supplier within 30 days after receiving the offer. If an owner fails to accept an offer within 30 days after receipt, the offer is deemed rejected. (2) If the […]

Section 701.585 – Effect of notice of defect on time for commencing court action.

(1) If an owner sends a contractor, subcontractor or supplier a notice of defect within the time allowed for the owner to commence a court action against that contractor, subcontractor or supplier for a claim described in ORS 701.565, the time for the owner to commence the action shall be extended, notwithstanding any statute of […]

Section 701.595 – Failure to follow notice of defect procedure.

If an owner compels arbitration or commences a court action against any contractor, subcontractor or supplier to assert a claim arising out of or related to the construction, alteration or repair of a residence located in this state and the owner has not followed the procedure set forth in ORS 701.565 and 701.575, the arbitrator […]