The legislature finds that in many areas of this state landowners, utilities and public authorities desire to convert existing overhead electric and communication facilities to underground facilities by means of special assessment proceedings. The legislature declares that a public purpose will be served and that the public welfare will be promoted by providing a procedure […]
As used in ORS 758.210 to 758.270, unless the context requires otherwise: (1) “Convert,” “converting” or “conversion” means the removal of overhead electric or communication facilities and the replacement thereof with underground electric or communication facilities at the same or different locations. (2) “Electric or communication facilities” means any works or improvements used or useful […]
(1) A public authority shall have the power to require the conversion of overhead electric or communication facilities to underground facilities; to provide and receive funds to pay for such conversion; and to assess the whole or any part of the cost thereof against the real property included in the underground assessment district specially benefited […]
(1) A proceeding for conversion may be initiated: (a) By a petition signed by not less than 60 percent of the landowners within the proposed assessment district who own not less than 60 percent of the land area within the district; or (b) By an ordinance or resolution of a public authority declaring its intention […]
(1) Upon presentation of the petition and certificate of sufficiency, or upon adoption of an ordinance or resolution, the public authority shall proceed in the manner provided by ORS 223.389. (2) Unless the charter of a county provides otherwise, a county shall declare a proposed conversion abandoned if, after notice as provided by ORS 223.389, […]
Unless otherwise provided by ORS 758.210 to 758.270, the provisions relating to the procedure for local improvements in cities, as set forth in ORS 223.205, 223.210 to 223.295, 223.387 to 223.399, 223.401, 223.405 to 223.485, 223.505 to 223.595, 223.610, 223.615 to 223.650 and 223.770, apply to proceedings for a conversion by a city or county […]
(1) When a public authority in accordance with ORS 758.230 determines that a conversion shall be made, it may contract with the utilities supplying electric or communication service within the underground assessment district to perform the conversion. A contract shall provide: (a) A description of the electric and communication facilities to be converted; (b) That […]
Upon completion of the conversion of the overhead electric or communication facilities on public lands and right of way to underground, the affected utility shall file a verified statement of the costs of such conversion with the public authority. The public authority shall adopt an ordinance assessing the whole or any part of the cost […]
(1) Any conversion of electric or communication service facilities, including service connections, located on a privately owned lot or parcel shall be made at the expense of the landowner by the utility owning the facility. The conversion shall be made in accordance with applicable safety rules, codes, regulations, tariffs or ordinances. The utility shall not […]
If the owner of any structure or improvement served from the overhead electric or communication service facilities within an underground assessment district does not grant the utility a permit or easement referred to in ORS 758.250 or if such an owner fails to convert to underground service facilities within 90 days after the mailing to […]
To the extent that the contract between the utility and the public authority provides that all or any part of the conversion work shall be performed by the utility, any statute or charter provision requiring competitive bidding and the award of a contract to the lowest responsible bidder does not apply. [1969 c.385 §11]
Once converted, no overhead electric or communication facilities shall be installed, maintained or operated in any underground assessment district except as authorized by ORS 758.210 to 758.270. [1969 c.385 §12]
ORS 758.210 to 758.270 are supplemental and cumulative of existing rights, laws, charters, ordinances and franchises and shall not abrogate or modify any franchise granted to a utility by any local government or abrogate or modify in any way existing rights, laws, charters or ordinances of any local government. [1969 c.385 §13]