§ 40-341 – Definitions

40-341. Definitions In this article, unless the context otherwise requires: 1. " Clerk" means the clerk of the board of supervisors or any person or officer who acts as clerk of the board of supervisors. 2. " Convert" or " conversion" means the removal of existing overhead electric or communication facilities and the replacement thereof […]

§ 40-343 – Petition of owners and petition of public service corporation or public agency for establishment of underground conversion service area; notice of proposed lien

40-343. Petition of owners and petition of public service corporation or public agency for establishment of underground conversion service area; notice of proposed lien A. Within ninety days after the joint report referred to in section 40-342 is made available to the petitioners, not less than sixty per cent of the owners of real property […]

§ 40-344 – Hearing on petition; notice

40-344. Hearing on petition; notice A. Upon receipt of a petition to establish an underground conversion service area, the corporation commission, board of supervisors or city or town council shall set a date for a hearing on the petition, which date shall be not later than sixty days nor sooner than thirty days after receipt […]

§ 40-346 – Hearing on petition by corporation commission, board of supervisors or city or town council; determination of economic and technical feasibility; addition or elimination of certain areas

40-346. Hearing on petition by corporation commission, board of supervisors or city or town council; determination of economic and technical feasibility; addition or elimination of certain areas A. The corporation commission, board of supervisors or city or town council, as the case may be, shall hold a hearing, upon notice as provided in this article, […]

§ 40-347 – Establishment of conversion costs; apportionment of costs; method of payment

40-347. Establishment of conversion costs; apportionment of costs; method of payment A. The order authorizing the establishment of the underground conversion service area shall authorize each public service corporation or public agency whose overhead electric or communication facilities are to be converted to charge the underground conversion costs to each lot or parcel of real […]

§ 40-350 – Lien for cost of conversion; procedure to perfect lien; recording notice of lien; default; limitation of action to foreclose lien; disconnection of service upon default

40-350. Lien for cost of conversion; procedure to perfect lien; recording notice of lien; default; limitation of action to foreclose lien; disconnection of service upon default A. Upon completion of the conversion of the overhead electric and communication facilities, the public service corporation or public agency shall determine the total conversion costs as provided in […]

§ 40-351 – Sale of property to satisfy lien

40-351. Sale of property to satisfy lien No sale of property to satisfy a lien granted under the provisions of this article shall be made except upon judgment of foreclosure and order of sale.

§ 40-352 – Relocation of underground facilities; public service corporation or public agency to be reimbursed for cost thereof

40-352. Relocation of underground facilities; public service corporation or public agency to be reimbursed for cost thereof When facilities converted to underground pursuant to this article are thereafter moved, relocated or removed to avoid interference with public works or improvements, the public service corporation or public agency owning such facilities shall be reimbursed by the […]

§ 40-353 – Application of article; reinstallation of overhead facilities prohibited

40-353. Application of article; reinstallation of overhead facilities prohibited A. The provisions of this article shall apply only to the relocation underground of existing utilities. B. Once removed, no overhead electric or communication facilities shall be installed in an underground conversion service area. C. Following the conversion of overhead electric or communication facilities, the public […]

§ 40-355 – Franchises, charters and ordinances of local governments not affected

40-355. Franchises, charters and ordinances of local governments not affected The provisions of this article shall be supplemental and cumulative of existing rights, laws, local charters, ordinances and franchises and shall not be deemed to abrogate or modify the provisions of any franchise granted to public service corporations by any local government or to abrogate […]

§ 40-356 – Nonseverability

40-356. Nonseverability If any provision of this article be held invalid, such invalidity shall invalidate this article in its entirety, and to this end the provisions of this article are declared to be nonseverable.