Section 8609.
8609. Any provision in a payment bond attempting by contract to shorten the period prescribed in Section 337 of the Code of Civil Procedure for the commencement of an action on the bond shall not be valid under either of the following circumstances: (a) If the provision attempts to limit the time for commencement of an […]
Section 8730.
8730. If the contract price for a work of improvement is not a fixed price, the amount of security provided under this chapter shall be the guaranteed maximum price or, if there is no guaranteed maximum price, the owner’s and direct contractor’s good faith estimate of the reasonable value of the work to be provided […]
Section 8610.
8610. Notwithstanding Section 8609, if a payment bond under this title is recorded before completion of a work of improvement, an action to enforce the liability on the bond may not be commenced later than six months after completion of the work of improvement. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective […]
Section 8800.
8800. (a) Except as otherwise agreed in writing by the owner and direct contractor, the owner shall pay the direct contractor, within 30 days after notice demanding payment pursuant to the contract is given, any progress payment due as to which there is no good faith dispute between them. The notice given shall comply with the […]
Section 8612.
8612. (a) In order to enforce a claim against a payment bond under this title, a claimant shall give the preliminary notice provided in Chapter 2 (commencing with Section 8200). (b) If preliminary notice was not given as provided in Chapter 2 (commencing with Section 8200), a claimant may enforce a claim by giving written notice to […]
Section 8802.
8802. (a) This section applies to a contract between a public utility and a direct contractor for all or part of a work of improvement. (b) Unless the direct contractor and a subcontractor otherwise agree in writing, within 21 days after receipt of a progress payment from the public utility the direct contractor shall pay the subcontractor […]
Section 8614.
8614. Notice to the principal and surety under Section 8612 shall comply with the requirements of Chapter 2 (commencing with Section 8100) of Title 1. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)
Section 8810.
8810. This article governs a retention payment withheld by an owner from a direct contractor or by a direct contractor from a subcontractor. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)
Section 8700.
8700. (a) This chapter applies if any of the following conditions is satisfied: (1) The owner of the fee interest in property contracts for a work of improvement on the property with a contract price greater than five million dollars ($5,000,000). (2) The owner of a less than fee interest in property, including a leasehold interest, contracts for […]
Section 8702.
8702. This chapter does not apply to any of the following works of improvement: (a) A single-family residence, including a single-family residence located within a subdivision, and any associated fixed work that requires the services of a general engineering contractor as defined in Section 7056 of the Business and Professions Code. As used in this subdivision, […]