Section 8612.

8612. (a) In order to enforce a claim against a payment bond under this title, a claimant shall give the preliminary notice provided in Chapter 2 (commencing with Section 8200). (b) If preliminary notice was not given as provided in Chapter 2 (commencing with Section 8200), a claimant may enforce a claim by giving written notice to […]

Section 8614.

8614. Notice to the principal and surety under Section 8612 shall comply with the requirements of Chapter 2 (commencing with Section 8100) of Title 1. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)

Section 8609.

8609. Any provision in a payment bond attempting by contract to shorten the period prescribed in Section 337 of the Code of Civil Procedure for the commencement of an action on the bond shall not be valid under either of the following circumstances: (a) If the provision attempts to limit the time for commencement of an […]

Section 8610.

8610. Notwithstanding Section 8609, if a payment bond under this title is recorded before completion of a work of improvement, an action to enforce the liability on the bond may not be commenced later than six months after completion of the work of improvement. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective […]

Section 8600.

8600. (a) This section applies if, before the commencement of work, the owner in good faith files a direct contract with the county recorder, and records a payment bond of the direct contractor in an amount not less than 50 percent of the price stated in the direct contract. (b) If the conditions of subdivision (a) are […]

Section 8602.

8602. Section 8600 does not preclude an owner from requiring a performance bond, payment bond, or other security as protection against a direct contractor’s failure to perform the direct contract or to make full payment for all work provided pursuant to the contract. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January […]

Section 8604.

8604. (a) If a lending institution requires that a payment bond be given as a condition of lending money to finance a work of improvement, and accepts in writing as sufficient a bond given in fulfillment of the requirement, the lending institution may not thereafter object to the borrower as to the validity of the bond […]

Section 8606.

8606. (a) A payment bond under this title shall be conditioned for the payment in full of the claims of all claimants and shall by its terms inure to the benefit of all claimants so as to give a claimant a right of action to enforce the liability on the bond. The bond shall be given […]

Section 8608.

8608. (a) This title does not give a claimant a right to recover on a direct contractor’s payment bond given under this chapter unless the claimant provided work to the direct contractor either directly or through one or more subcontractors, pursuant to a direct contract. (b) Nothing in this section affects the stop payment notice right of, […]