Section 9306.
9306. If the contract of any subcontractor on a particular work of improvement provides for payment to the subcontractor of more than four hundred dollars ($400), the failure of that subcontractor, licensed under the Contractors’ State License Law (Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code), to give […]
Section 9300.
9300. (a) Except as otherwise provided by statute, before giving a stop payment notice or asserting a claim against a payment bond, a claimant shall give preliminary notice to the following persons: (1) The public entity. (2) The direct contractor to which the claimant provides work. (b) Notwithstanding subdivision (a): (1) A laborer is not required to give preliminary notice. […]
Section 9302.
9302. (a) Except as provided in subdivision (b), preliminary notice shall be given in compliance with the requirements of Chapter 2 (commencing with Section 8100) of Title 1. (b) If the public works contract is for work constructed by the Department of Public Works or the Department of General Services of the state, preliminary notice to the […]
Section 9303.
9303. The preliminary notice shall comply with the requirements of Section 8102, and shall also include: (a) A general description of the work to be provided. (b) An estimate of the total price of the work provided and to be provided. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July […]
Section 9304.
9304. A claimant may give a stop payment notice or assert a claim against a payment bond only for work provided within 20 days before giving preliminary notice and at any time thereafter. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of […]