US Lawyer Database

Section 9566.

9566. (a) A claimant does not have a right to recover on a payment bond unless the claimant provided work to the direct contractor either directly or through one or more subcontractors pursuant to a public works contract. (b) Nothing in this section affects the stop payment notice rights of, and relative priorities among, design professionals. (Added […]

Section 9550.

9550. (a) A direct contractor that is awarded a public works contract involving an expenditure in excess of twenty-five thousand dollars ($25,000) shall, before commencement of work, give a payment bond to and approved by the officer or public entity by whom the contract was awarded. (b) A public entity shall state in its call for bids […]

Section 9552.

9552. If a payment bond is not given and approved as required by Section 9550: (a) Neither the public entity awarding the public works contract nor any officer of the public entity shall audit, allow, or pay a claim of the direct contractor pursuant to the contract. (b) A claimant shall receive payment of a claim pursuant […]

Section 9554.

9554. (a) A payment bond shall be in an amount not less than 100 percent of the total amount payable pursuant to the public works contract. The bond shall be in the form of a bond and not a deposit in lieu of a bond. The bond shall be executed by an admitted surety insurer. (b) The […]

Section 9558.

9558. A claimant may commence an action to enforce the liability on the bond at any time after the claimant ceases to provide work, but not later than six months after the period in which a stop payment notice may be given under Section 9356. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) […]

Section 9560.

9560. (a) In order to enforce a claim against a payment bond, a claimant shall give the preliminary notice provided in Chapter 3 (commencing with Section 9300). (b) If preliminary notice was not given as provided in Chapter 3 (commencing with Section 9300), a claimant may enforce a claim by giving written notice to the surety and […]

Section 9562.

9562. Notice to the principal and surety under Section 9560 shall comply with the requirements of Chapter 2 (commencing with Section 8100) of Title 1. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)

Section 9564.

9564. (a) A claimant may maintain an action to enforce the liability of a surety on a payment bond whether or not the claimant has given the public entity a stop payment notice. (b) A claimant may maintain an action to enforce the liability on the bond separately from and without commencement of an action against the […]