Section 9554.

9554. (a) A payment bond shall be in an amount not less than 100 percent of the total amount payable pursuant to the public works contract. The bond shall be in the form of a bond and not a deposit in lieu of a bond. The bond shall be executed by an admitted surety insurer. (b) The […]

Section 9303.

9303. The preliminary notice shall comply with the requirements of Section 8102, and shall also include: (a) A general description of the work to be provided. (b) An estimate of the total price of the work provided and to be provided. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July […]

Section 9304.

9304. A claimant may give a stop payment notice or assert a claim against a payment bond only for work provided within 20 days before giving preliminary notice and at any time thereafter. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of […]

Section 9306.

9306. If the contract of any subcontractor on a particular work of improvement provides for payment to the subcontractor of more than four hundred dollars ($400), the failure of that subcontractor, licensed under the Contractors’ State License Law (Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code), to give […]

Section 9350.

9350. The rights of all persons furnishing work pursuant to a public works contract, with respect to any fund for payment of construction costs, are governed exclusively by this chapter, and no person may assert any legal or equitable right with respect to that fund, other than a right created by direct written contract between […]

Section 9352.

9352. (a) A stop payment notice shall comply with the requirements of Chapter 2 (commencing with Section 8100) of Title 1, and shall be signed and verified by the claimant. (b) The notice shall include a general description of work to be provided, and an estimate of the total amount in value of the work to be […]

Section 9354.

9354. (a) Except as provided in subdivision (b), a stop payment notice shall be given in compliance with the requirements of Chapter 2 (commencing with Section 8100) of Title 1. (b) A stop payment notice shall be given to the public entity by giving the notice to the following person: (1) In the case of a public works […]

Section 9356.

9356. A stop payment notice is not effective unless given before the expiration of whichever of the following time periods is applicable: (a) If a notice of completion, acceptance, or cessation is recorded, 30 days after that recordation. (b) If a notice of completion, acceptance, or cessation is not recorded, 90 days after cessation or completion. (Added […]

Section 9358.

9358. (a) The public entity shall, on receipt of a stop payment notice, withhold from the direct contractor sufficient funds due or to become due to the direct contractor to pay the claim stated in the stop payment notice and to provide for the public entity’s reasonable cost of any litigation pursuant to the stop payment […]

Section 9360.

9360. (a) This chapter does not prohibit payment of funds to a direct contractor or a direct contractor’s assignee if a stop payment notice is not received before the disbursing officer actually surrenders possession of the funds. (b) This chapter does not prohibit payment of any amount due to a direct contractor or a direct contractor’s assignee […]