Section 8848.
8848. (a) This article applies to a contract entered into on or after January 1, 1999. (b) This article does not apply to a retention withheld by a lender pursuant to a construction loan agreement. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of […]
Section 8812.
8812. (a) If an owner withholds a retention from a direct contractor, the owner shall, within 45 days after completion of the work of improvement, pay the retention to the contractor. (b) If part of a work of improvement ultimately will become the property of a public entity, the owner may condition payment of a retention allocable […]
Section 9000.
9000. This title applies to a work of improvement contracted for by a public entity. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)
Section 8814.
8814. (a) If a direct contractor has withheld a retention from one or more subcontractors, the direct contractor shall, within 10 days after receiving all or part of a retention payment, pay to each subcontractor from whom retention has been withheld that subcontractor’s share of the payment. (b) If a retention received by the direct contractor is […]
Section 9100.
9100. (a) Except as provided in subdivision (b), any of the following persons that have not been paid in full may give a stop payment notice to the public entity or assert a claim against a payment bond: (1) A person that provides work for a public works contract, if the work is authorized by a direct […]
Section 8816.
8816. (a) If the direct contractor gives the owner, or a subcontractor gives the direct contractor, notice that work in dispute has been completed in accordance with the contract, the owner or direct contractor shall within 10 days give notice advising the notifying party of the acceptance or rejection of the disputed work. Both notices shall […]
Section 9200.
9200. For the purpose of this title, completion of a work of improvement occurs at the earliest of the following times: (a) Acceptance of the work of improvement by the public entity. (b) Cessation of labor on the work of improvement for a continuous period of 60 days. This subdivision does not apply to a contract awarded […]
Section 8818.
8818. If an owner or direct contractor does not make a retention payment within the time required by this article: (a) The owner or direct contractor is liable to the person to which payment is owed for a penalty of 2 percent per month on the amount wrongfully withheld, in place of any interest otherwise due. […]
Section 9202.
9202. (a) A public entity may record a notice of cessation if there has been a continuous cessation of labor for at least 30 days prior to the recordation that continues through the date of the recordation. (b) The notice shall be signed and verified by the public entity or its agent. (c) The notice shall comply with […]
Section 8820.
8820. It is against public policy to waive the provisions of this article by contract. (Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)