4410. In the event a national emergency occurs, and public work, being performed by contract, is stopped, directly or indirectly, because of the freezing or diversion of materials, equipment or labor, as the result of an order or a proclamation of the President of the United States, or of an order of any federal authority, […]
4411. Such an agreement shall include the terms and conditions of the termination of the contract and provision for the payment of compensation or money, if any, which either party shall pay to the other or any other person, under the facts and circumstances in the case. Compensation to the contractor shall be determined on […]
4412. It shall be competent for any public agency to provide in the specifications for any public works contract detailed provisions as to the conditions under which the contractor shall be entitled, as a matter of right, to termination of the contract on account of conditions such as are described in Section 4410 and as […]