25199. (a) The Legislature finds and declares as follows: (1) Existing laws require numerous permits before a hazardous waste facility can be constructed and operated. The permits are issued by governmental agencies, at both the state and local levels under land use planning, zoning, hazardous waste, air quality, water quality, and solid waste management laws. […]
25199.1. Unless the context otherwise requires, the following definitions govern the construction of this article: (a) “Appeal board” means an appeal board established pursuant to Section 25199.10. (b) “Hazardous waste facility project” means a project undertaken for the purpose of siting and constructing a new hazardous waste facility that will require a hazardous waste facilities […]
25199.10. (a) If an appeal is filed pursuant to subdivision (b), (d), or (e) of Section 25199.9, or paragraph (3) of subdivision (c) of Section 25199.9, the Governor or the Governor’s designee shall determine within five working days whether the proponent has obtained all permits for the specified hazardous waste facility project which can be […]
25199.11. (a) An appeal board convened by the Governor or the Governor’s designee to hear an appeal pursuant to subdivision (b) or (c) of Section 25199.9 shall follow the procedures and requirements specified in this section. (b) Within 30 days after the Governor or the Governor’s designee determines that an appeal board should be convened […]
25199.13. (a) An appeal board convened by the Governor or the Governor’s designee to hear an appeal pursuant to subdivision (d) or (e) of Section 25199.9 shall follow the procedures and requirements specified in this section. (b) Within 30 days after the Governor or the Governor’s designee determines that an appeal board should be convened […]
25199.14. The final decision of the appeal board concerning an appeal authorized pursuant to Section 25199.9 shall be deemed to be the final administrative action of the appeal board. (Added by Stats. 1986, Ch. 1504, Sec. 8.)
25199.2. Except as otherwise provided in this article, Chapter 4.5 (commencing with Section 65920) of Division 1 of Title 7 of the Government Code applies to all public agencies which make a land use decision or issue a permit for a hazardous waste facility project, as specified in Section 65963.1 of the Government Code. The […]
25199.3. (a) Notwithstanding any other provision of law, an applicant for a hazardous waste facility project may submit applications for a land use decision and for one or more permits to the appropriate public agencies simultaneously. Unless a state agency is prohibited by statute from approving a permit before the granting of a local land […]
25199.5. (a) At the request of an applicant, the legislative body of a local agency shall, within 60 calendar days after the local agency has determined that an application for a land use decision for a hazardous waste facility project is complete, issue an initial written determination on whether the hazardous waste facility project is […]
25199.6. (a) Section 65943 of the Government Code does not apply to the department’s review of applications for a hazardous waste facilities permit. The department shall review for completeness each application for a hazardous waste facilities permit and notify the applicant in writing whether the application is complete within 30 days from the date of […]
25199.7. (a) At least 90 days before filing an application for a land use decision for a specified hazardous waste facility project with a local agency, the proponent shall file a notice of intent to make the application with the Department of Toxic Substances Control and with the applicable city or county. The notice of intent […]
25199.8. (a) If an action or proceeding has been commenced in any court to attack, review, set aside, void, or annul the acts or decisions of a lead agency for a specified hazardous waste facility project on the grounds of noncompliance with Division 13 (commencing with Section 21000) of the Public Resources Code, the proponent […]
25199.9. (a) A proponent may file an appeal of a land use decision made by a local agency for a specified hazardous waste facility project with the Governor or the Governor’s designee pursuant to subdivision (b), (c), or (d) and any interested person may file an appeal of a land use decision made by a […]