Section 22172.
22172. The procurement process for progressive design-build projects shall progress as follows: (a) The local agency shall prepare and issue a request for qualifications in order to select a design-build entity to execute the project. The request for qualifications shall include, but is not limited to, the following elements: (1) Documentation of the size, type, and desired […]
Section 22172.1.
22172.1. (a) The design-build entity shall provide payment and performance bonds for the project in the form and in the amount required by the local agency, and issued by a California admitted surety. The amount of the payment bond shall not be less than the amount of the performance bond. (b) The design-build contract shall require errors […]
Section 22172.2.
22172.2. (a) After selecting a design-build entity based upon qualifications, the local agency may enter into a contract and direct the design-build entity to begin design and preconstruction activities sufficient to establish a guaranteed maximum price for the project. (b) (1) Upon agreement of the guaranteed maximum price for the project, the local agency, at its sole and […]
Section 22172.3.
22172.3. (a) The local agency, in each design-build request for qualifications, may identify specific types of subcontractors that shall be included in the design-build entity’s statement of qualifications. All construction subcontractors that are identified in the statement of qualifications shall be afforded the protections of Chapter 4 (commencing with Section 4100) of Part 1. (b) Following award […]
Section 22172.4.
22172.4. (a) If the local agency elects to award a project pursuant to this chapter, retention proceeds withheld by the local agency from the design-build entity shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation. Work performed to establish the guaranteed maximum price […]
Section 22172.5.
22172.5. (a) Notwithstanding Section 10231.5 of the Government Code, no later than January 1, 2028, a local agency that uses the progressive design-build process pursuant to this chapter shall submit to the appropriate policy and fiscal committees of the Legislature a report on the use of the progressive design-build process. (b) The report shall include, but is […]
Section 22173.
22173. Nothing in this chapter affects, expands, alters, or limits any rights or remedies otherwise available at law. (Added by Stats. 2022, Ch. 243, Sec. 1. (SB 991) Effective January 1, 2023. Repealed as of January 1, 2029, pursuant to Section 22174.)
Section 22164.
22164. The procurement process for the design-build projects shall progress as follows: (a) (1) The local agency shall prepare a set of documents setting forth the scope and estimated price of the project. The documents may include, but need not be limited to, the size, type, and desired design character of the project, performance specifications covering the […]
Section 22174.
22174. This chapter shall remain in effect only until January 1, 2029, and as of that date is repealed. (Added by Stats. 2022, Ch. 243, Sec. 1. (SB 991) Effective January 1, 2023. Repealed as of January 1, 2029, by its own provisions. Note: Repeal affects Chapter 4.1, commencing with Section 22170.)
Section 22109.
22109. Any contract for electronic data-processing goods and services, to be manufactured or performed by the contractor especially for the district and not suitable for sale to others in the ordinary course of the contractor’s business, may provide for such terms and conditions as the district deems necessary to protect its interests including, but not […]