Section 6450.
6450. Any dam which the department finds was not 90 percent constructed on August 14, 1929 shall be subject to the same provisions as a dam commenced after that date. (Enacted by Stats. 1943, Ch. 368.)
6450. Any dam which the department finds was not 90 percent constructed on August 14, 1929 shall be subject to the same provisions as a dam commenced after that date. (Enacted by Stats. 1943, Ch. 368.)
6451. Construction work on such a dam may proceed, if an application for approval thereof is filed, until an order from the department is received approving the dam or specifying how its construction must be made or altered to render it safe. After receipt of an order directing the construction of such a dam, work […]
6452. Dams found to be 90 per cent or more constructed on August 14, 1929 shall be subject to the same supervision as dams which were completed prior to that date. (Enacted by Stats. 1943, Ch. 368.)