§ 33.2-1104. Application of article; existing contracts

The provisions of this article shall apply to all contracts executed and proceedings initiated after June 30, 1976, and may be made applicable to existing contracts by mutual consent of the contracting parties. 1976, c. 230, § 33.1-388; 1982, c. 320; 2014, c. 805.

§ 33.2-1105. Provisions of article deemed part of contract

The provisions of this article shall be deemed to enter into and form a part of every contract entered into between the Board and any contractor on or after July 1, 1976, and no provision in said contracts shall be valid that is in conflict herewith. 1976, c. 230, § 33.1-389; 2014, c. 805.

§ 33.2-1101. Submission of claims; initial investigation and notice of decision; appearance before Commissioner of Highways; further investigation and notice of decision; settlement

A. Upon the completion of any contract for the construction of any state highway project awarded by the Board or by the Commissioner of Highways to any contractor, if the contractor fails to receive such settlement as he claims to be entitled to under the contract for himself or for his subcontractors or for persons […]

§ 33.2-1102. Limitation of suits on contracts

No suit or action shall be brought against the Department by a contractor or any persons claiming under him or on behalf of a subcontractor of the contractor or a person furnishing materials for the contract to the contractor on any contract executed pursuant to this article or by others on any claim arising from […]

§ 33.2-1103. Civil action

As to such portion of the claim as is denied by the Commissioner of Highways, the contractor may institute a civil action for such sum as he claims to be entitled to under the contract for himself or for his subcontractors or for persons furnishing materials for the contract by the filing of a petition […]

§ 33.2-1100. Highway construction contracts

A. Every contractor whose bid is accepted shall, before commencing work, enter into a contract with the Commissioner of Highways that shall fully set out the time when work shall commence and when the contract shall be completed as well as the time and manner for the payment for the work. Whenever the Commissioner of […]