§ 43-26. Assignee’s rights

Any assignee of such a claim as is mentioned in the preceding sections may file the memorandum and make the oath required by such sections, and shall have the same rights as his assignor. Code 1919, § 6440.

§ 43-25. Perfection and enforcement of lien

No person shall be entitled to the lien given by § 43-24 unless he shall, within ninety days after the last item of his bill becomes due and payable for which such supplies are furnished or service rendered, file in the clerk’s office of the circuit court of the county or circuit court of the […]

§ 43-23.1. Forfeiture of lien

Any person who shall, with intent to mislead, include in his memorandum of lien work not performed upon, or materials not furnished for, the property described in his memorandum shall thereby forfeit any right to a lien under this chapter. 1968, c. 568; 1976, c. 253.

§ 43-23.2. Remedies cumulative

The remedies afforded by this chapter shall be deemed cumulative in nature and not be construed to be in lieu of any other legal or equitable remedies. 1968, c. 568.

§ 43-24. Liens of employees, suppliers, etc.

All conductors, brakemen, engine drivers, firemen, captains, stewards, pilots, clerks, depot or office agents, storekeepers, mechanics, traveling representatives or laborers, and all persons furnishing railroad iron, engines, cars, fuel and all other supplies necessary to the operation of any railway, canal or other transportation company, and all clerks, mechanics, traveling representatives, foremen, and laborers, and […]

§ 43-20. Extent of lien where owner has less than fee in land

Subject to the provisions of § 43-3, if the person who shall cause a building or structure to be erected or repaired owns less than a fee simple estate in the land, then only his interest therein shall be subject to liens created under this chapter. When the vendee under a contract for the sale […]

§ 43-21. Priorities between mechanics’ and other liens

No lien or encumbrance upon the land created before the work was commenced or materials furnished shall operate upon the building or structure erected thereon, or materials furnished for and used in the same, until the lien in favor of the person doing the work or furnishing the materials shall have been satisfied; nor shall […]

§ 43-22. How liens enforced

The liens created and perfected under this chapter may be enforced in a court of equity by a bill filed in the county or city wherein the building, structure, or railroad, or some part thereof is situated, or wherein the owner, or if there be more than one, any of them, resides. The plaintiff shall […]

§ 43-23. Priority among liens perfected under this chapter

There shall be no priority among the liens created and perfected under this chapter, except that the lien of a subcontractor shall be preferred to that of his general contractor; the lien of persons performing labor or furnishing materials for a subcontractor, shall be preferred to that of such subcontractor; and liens filed by persons […]