§ 56-614. Definitions

As used in this chapter, unless the context requires a different meaning: “Distribution facilities” includes poles and wires, or cables, or pipelines or other underground conduits by which a renewable generator is able to (i) supply electricity generated at its renewable energy facility to the electric distribution grid, (ii) distribute steam generated at its renewable […]

§ 56-615. Right to occupy rights-of-way; location of rights-of-way

A. Every renewable generator shall have authority to occupy and use the public roads, works, turnpikes, streets, avenues, and alleys in any county, with the consent of the board of supervisors or other governing authority thereof, or in any incorporated city or town, with the consent of the council thereof, and the waterways within the […]

§ 56-617. Public rights-of-way use fee

A. Notwithstanding any other provisions of law, there is hereby established a public rights-of-way use fee to be charged in lieu of any and all fees of general application, except for zoning, subdivision, site plan, and comprehensive plan fees of general application, otherwise chargeable to a renewable generator by the Department of Transportation or a […]

§ 56-618. Reimbursement for relocation costs

A. Renewable generators shall be reimbursed 100 percent of the eligible cost of relocating distribution facilities installed in the public rights-of-way, for the first three years after the completion of the installation, that are incurred at the direction of a locality that imposes by ordinance the public rights-of-way use fee or the Department of Transportation […]

§ 56-620. How consent of appropriate authorities obtained; terms of use

The consent required under § 56-615, when given, shall be by ordinance regularly adopted by the council or other governing body of the city or town or by resolution regularly adopted and spread upon the minutes by the board of supervisors or other governing authority of the county in which such line is to be […]

§ 56-621. Cost to Commonwealth in connection with inspection and coordination of construction of line to be paid by renewable generator

The actual costs and expenses of the Commonwealth for the inspection or coordination of the construction or installation of any of the distribution facilities of the renewable generator, under the provisions of this chapter, under any permit of the Commonwealth Transportation Board shall be borne by the renewable generator. The sum of the payment required […]

§ 56-622. Renewable generator may contract for right-of-way

A renewable generator may contract with any person that owns lands, or any interest, franchise, privilege, or easement therein or in respect thereto, over which distribution facilities are proposed to be constructed, for the right-of-way for erecting, repairing, and preserving its poles and other structures necessary for operating its facilities, and for sufficient land for […]

§ 56-623. Construction of transmission facilities

All posts, poles, wires, cables, lines, pipelines, conduits, and other distribution facilities erected under any authority conferred by this chapter shall be so located as in no way to obstruct or interfere with public travel or the ordinary use of, or the safety and convenience of persons traveling through, on, or over, the public roads, […]

§ 56-624. Restoring condition of ground

The portions of the surface of the roads, turnpikes, streets, avenues, or alleys, or of any pavements opened up or disturbed in erecting, repairing, laying, or replacing distribution facilities under the provisions of this chapter shall be immediately restored to and maintained in good condition by the renewable generator doing such work. In case of […]