1013.79 – University Facility Enhancement Challenge Grant Program.
1013.79 University Facility Enhancement Challenge Grant Program.— (1) The Legislature recognizes that the universities do not have sufficient physical facilities to meet the current demands of their instructional and research programs. It further recognizes that, to strengthen and enhance universities, it is necessary to provide facilities in addition to those currently available from existing revenue sources. It […]
1013.81 – Florida College System institution indebtedness; bonds and tax anticipation certificates; payment.
1013.81 Florida College System institution indebtedness; bonds and tax anticipation certificates; payment.— (1) The indebtedness incurred for the benefit of Florida College System institutions and represented by bonds or motor vehicle tax anticipation certificates issued from time to time by the State Board of Education, hereinafter called “state board,” pursuant to s. 18, Art. XII of the […]
1013.82 – Contracts of institutions for supplies, utility services, and building construction exempt from operation of county or municipal ordinance or charter.
1013.82 Contracts of institutions for supplies, utility services, and building construction exempt from operation of county or municipal ordinance or charter.— (1) University boards of trustees are authorized to contract for supplies, utility services, and building construction without regulation or restriction by municipal or county charter or ordinance. Contractual arrangements shall be in the best interests of […]
1013.67 – Commissioner to provide for encumbrances of funds.
1013.67 Commissioner to provide for encumbrances of funds.—The Commissioner of Education shall provide for timely encumbrances of funds for duly authorized projects. Encumbrances may include proceeds to be received under a resolution approved by the State Board of Education authorizing the issuance of 1997 school capital outlay bonds pursuant to s. 11(d), Art. VII of the […]
1013.841 – End of year balance of Florida College System institution funds.
1013.841 End of year balance of Florida College System institution funds.— (1) Unexpended amounts in any fund in any Florida College System institution current year state operating budget shall be carried forward and included as the balance forward for that fund in the approved operating budget for the following year. (2)(a) Each Florida College System institution with a […]
1013.68 – Classrooms First Program; uses.
1013.68 Classrooms First Program; uses.— (1) The Commissioner of Education shall allocate funds appropriated for the Classrooms First Program among the district school boards. It is the intent of the Legislature that this program be administered as nearly as practicable in the same manner as the capital outlay program authorized under s. 9(d), Art. XII of the […]
1013.69 – Full bonding required to participate in programs.
1013.69 Full bonding required to participate in programs.—Any district with unused bonding capacity in its Capital Outlay and Debt Service Trust Fund allocation that certifies in its district educational facilities plan that it will not be able to meet all of its need for new student stations within existing revenues must fully bond its Capital Outlay […]
1013.47 – Substance of contract; contractors to give bond; penalties.
1013.47 Substance of contract; contractors to give bond; penalties.—Each board shall develop contracts consistent with this chapter and statutes governing public facilities. Such a contract must contain the drawings and specifications of the work to be done and the material to be furnished, the time limit in which the construction is to be completed, the time […]
1013.48 – Changes in construction requirements after award of contract.
1013.48 Changes in construction requirements after award of contract.—The board may, at its option and by written policy duly adopted and entered in its official minutes, authorize the superintendent or president or other designated individual to approve change orders in the name of the board for preestablished amounts. Approvals shall be for the purpose of expediting […]
1013.50 – Final payment to contractor.
1013.50 Final payment to contractor.— (1) The final payment to the contractor shall not be made until the construction project has been inspected by the architect or other person designated by the board for that purpose and until he or she has issued a written certificate that the project has been constructed in accordance with the approved […]