US Lawyer Database

403.9425 – Revocation or suspension of certification.

403.9425 Revocation or suspension of certification.—Any certification may be revoked or suspended: (1) For any material false statement in the application or in the supplemental or additional statements of fact or studies required of the applicant when a true answer would have warranted the board’s refusal to recommend a certification in the first instance. (2) For failure to […]

403.941 – Preliminary statements of issues, reports, and studies.

403.941 Preliminary statements of issues, reports, and studies.— (1) Each affected agency which received an application in accordance with s. 403.9407(3) shall submit a preliminary statement of issues to the department and the applicant no later than 60 days after distribution of the complete application. Such statements of issues shall be made available to each local government […]

403.973 – Expedited permitting; amendments to comprehensive plans.

403.973 Expedited permitting; amendments to comprehensive plans.— (1) It is the intent of the Legislature to encourage and facilitate the location and expansion of those types of economic development projects which offer job creation and high wages, strengthen and diversify the state’s economy, and have been thoughtfully planned to take into consideration the protection of the state’s […]

403.9411 – Notice; proceedings; parties and participants.

403.9411 Notice; proceedings; parties and participants.— (1)(a) No later than 15 days after an application has been determined complete, the applicant shall arrange for publication of a notice of the application and of the proceedings required by ss. 403.9401-403.9425. Such notice shall give notice of the provisions of s. 403.9416(1) and (2). (b) The applicant shall arrange for […]

403.9412 – Alternate corridors.

403.9412 Alternate corridors.— (1) No later than 50 days prior to the originally scheduled certification hearing, any party may propose alternate natural gas transmission pipeline corridor routes for consideration pursuant to ss. 403.9401-403.9425. (a) A notice of any such proposed alternate corridor shall be filed with the administrative law judge, all parties, and any local governments in whose […]

403.9413 – Amendment to the application.

403.9413 Amendment to the application.— (1) Any amendment made to the application shall be sent by the applicant to the administrative law judge and to all parties to the proceeding. (2) Any amendment to the application made prior to certification shall be disposed of as part of the original certification proceeding. Amendment of the application may be considered […]

403.9414 – Alteration of time limits.

403.9414 Alteration of time limits.—Any time limitation in ss. 403.9401-403.9425 may be altered by the administrative law judge upon stipulation between the department and the applicant unless objected to by any party within 5 days after notice or for good cause shown. History.—s. 1, ch. 92-284; s. 179, ch. 96-410.

403.9415 – Final disposition of application.

403.9415 Final disposition of application.— (1) Within 60 days after receipt of the administrative law judge’s recommended order, the board shall act upon the application by written order, approving in whole, approving with such conditions as the board deems appropriate, or denying the certification and stating the reasons for issuance or denial. (2) The issues that may be […]

403.9401 – Short title.

403.9401 Short title.—Sections 403.9401-403.9425 may be cited as the “Natural Gas Transmission Pipeline Siting Act.” History.—s. 1, ch. 92-284.

403.9402 – Legislative intent.

403.9402 Legislative intent.—It is the Legislature’s intent by adoption of ss. 403.9401-403.9425 to establish a centralized and coordinated permitting process for the location of natural gas transmission pipeline corridors and the construction and maintenance of natural gas transmission pipelines, which necessarily involves several broad interests of the public addressed through the subject matter jurisdiction of several […]