US Lawyer Database

§ 32-2-78. Definitions

As used in this part, the term: “Alternative contracting method” means a method of contracting authorized by Code Section 32-2-82. “Construction manager/general contractor” means a person the department has selected to perform project delivery pursuant to Code Section 32-2-82. “Participating local governing authority” includes the governing authority of any county or municipality whose geographical jurisdiction […]

§ 32-2-80. Public-Private Partnerships (P3s)

The department shall evaluate a potential project to determine, in the judgment of the department, appropriate or desirable levels of state, local, and private participation in financing such project. In making such determination, the department shall be authorized and encouraged to seek the advice and input of the affected local governing authorities, applicable metropolitan planning […]

§ 32-2-81. Design-Build Procedure

As used in this Code section, the term “design-build procedure” means a method of contracting under which the department contracts with another party for the party to both design and build the structures, facilities, systems, and other items specified in the contract. The department may use the design-build procedure for projects that include buildings, bridges […]

§ 32-2-82. Alternative Contracting Method

The department shall be authorized to utilize an alternative contracting method for project delivery that includes one of the following: An agreement in which a construction manager/general contractor performs two phases of work as follows: The first phase, in which the construction manager/general contractor performs in the capacity of a construction manager, consisting of preconstruction […]