672E-9 Additional construction defects.
§672E-9 Additional construction defects. A construction defect discovered after the notice of claim is served may not be alleged in an action until the claimant has given the contractor: (1) A written notice of claim regarding the alleged defect under section 672E-3; and (2) An opportunity to repair the construction defect or reject the notice […]
672E-10 Release.
§672E-10 Release. If the parties resolve the claim in whole or in part, the claimant shall be barred from bringing an action for the resolved claims. [L 2004, c 119, pt of §2]
672E-11 Contract of sale; provisions.
§672E-11 Contract of sale; provisions. (a) Upon entering into a contract for sale of a new structure or the construction or substantial remodeling of a premises, the seller of the new structure shall provide to the purchaser of the new structure, and the contractor of the construction or substantial remodeling of the premises shall provide […]
672E-12 Other actions.
§672E-12 Other actions. This chapter shall not interfere with a contractor’s right to seek contribution, indemnity, or recovery against a subcontractor, supplier, or design professional for any claim made against a contractor by a claimant. [L 2004, c 119, pt of §2]
672B-14 Immunity of panel members from liability.
§672B-14 Immunity of panel members from liability. No member of a design claim conciliation panel shall be liable in damages for libel, slander, or other defamation of character of any party to a design claim conciliation panel proceeding for any action taken or any decision, conclusion, finding, or recommendation made by the member while acting […]
672E-13 Dismissal without prejudice.
§672E-13 Dismissal without prejudice. The court or arbitrator shall dismiss, without prejudice, any action failing to meet the requirements of this chapter, unless: (1) The failure to meet the requirements is the direct result of the wrongful conduct of another party; (2) Circumstances beyond the control of the party prevented compliance; or (3) An applicable […]
672B-15 Statute of limitations tolled.
§672B-15 Statute of limitations tolled. The filing of the claim with the design claim conciliation panel or with an approved alternative dispute resolution provider shall toll any applicable statute of limitations, and any such statute of limitations shall remain tolled until sixty days after the date of the decision of the panel or the notification […]
673-1 Waiver of immunity.
§673-1 Waiver of immunity. (a) The State waives its immunity for any breach of trust or fiduciary duty resulting from the acts or omissions of its agents, officers and employees in the management and disposition of trust funds and resources of: (1) The Hawaiian home lands trust under article XII, sections 1, 2, and 3 […]
671D-14 Construction.
§671D-14 Construction. (a) Except as specifically provided in this part, nothing in this part shall be construed as changing the liabilities or immunities under law. (b) Nothing in this part shall be construed as requiring health care entities to provide clinical privileges to any or all classes or types of physicians or other licensed health […]
672B-1 Definitions.
§672B-1 Definitions. As used in this chapter: “Department” means the department of commerce and consumer affairs. “Design professional” means a professional engineer, architect, surveyor, or landscape architect licensed under chapter 464. “Director” means the director of commerce and consumer affairs. [L 2007, c 207, pt of §2]