Section 61-1708 – EFFECT OF ISSUANCE OF ROUTE CERTIFICATION.

61-1708. EFFECT OF ISSUANCE OF ROUTE CERTIFICATION. (1) Subject to any conditions attached to the certificate by the commission, a final commission order granting a route certificate shall bind the state and each of its agencies, divisions, bureaus, commissions, boards and local governments as to the approval of the authorized transmission route and the construction […]

Section 61-1709 – COMMISSION PROCEDURES — ADMINISTRATIVE REMEDY — RECONSIDERATION — JUDICIAL REVIEW.

61-1709. COMMISSION PROCEDURES — ADMINISTRATIVE REMEDY — RECONSIDERATION — JUDICIAL REVIEW. (1) All matters arising under this chapter shall be governed by the commission’s rules of procedure. (2) The commission’s proceeding to review an application for a route certificate for the construction of transmission facilities in a designated national interest electric transmission corridor shall constitute […]

Section 61-1609 – SUCCESSORS.

61-1609. SUCCESSORS. Any successor to the public utility, whether pursuant to any bankruptcy, reorganization or other insolvency proceeding, or pursuant to any merger, sale or transfer, by operation of law or otherwise, shall perform and satisfy all obligations of the public utility pursuant to this chapter in the same manner and to the same extent […]

Section 61-1610 – DISCLAIMER OF STATE FULL FAITH AND CREDIT.

61-1610. DISCLAIMER OF STATE FULL FAITH AND CREDIT. Cost reduction rates, cost reduction property, and any related cost reduction instruments issued under this chapter and any applicable cost reduction orders do not constitute a debt or liability of this state or of any political subdivision thereof and do not constitute a pledge of the full […]

Section 61-1611 – SEVERABILITY.

61-1611. SEVERABILITY. If any provision of this act or its application to any person or circumstance is held invalid, the remainder of the act or the application of the provision to other persons or circumstances is not affected. History: [61-1611, added 2005, ch. 372, sec. 1, p. 1194.]

Section 61-1701 – LEGISLATIVE PURPOSES AND FINDINGS.

61-1701. LEGISLATIVE PURPOSES AND FINDINGS. (1) The provisions of this chapter apply to the construction or modification of transmission facilities located in a national interest electric transmission corridor designated by the secretary of the United States department of energy under section 1221 of the energy policy act of 2005. The purpose of this chapter is […]

Section 61-1702 – DEFINITIONS.

61-1702. DEFINITIONS. (1) "Affected landowner" includes owners of property interests, as reflected in the most recent county or city tax records as receiving the tax notice, whose property: (a) Is directly affected, either crossed or used, by the proposed transmission line, including all facility sites, rights-of-way, access roads and temporary work spaces; and (b) Abuts […]

Section 61-1703 – COMMISSION AUTHORITY — PREEMPTION — RULES.

61-1703. COMMISSION AUTHORITY — PREEMPTION — RULES. (1) In the event that the secretary designates a national interest electric transmission corridor within Idaho, the public utilities commission is authorized to review the siting of all electric transmission facilities within such federally designated corridor. After notice and an opportunity for hearing, the commission shall review and […]

Section 61-1507 – SUCCESSORS.

61-1507. SUCCESSORS. Any successor to the public utility, whether pursuant to any bankruptcy, reorganization or other insolvency proceeding, or pursuant to any merger, sale or transfer, by operation of law or otherwise, shall perform and satisfy all obligations of the public utility pursuant to this chapter in the same manner and to the same extent […]

Section 61-1704 – NOTICE OF INTENT TO FILE — CONTENT — PREFILING PROCEDURES.

61-1704. NOTICE OF INTENT TO FILE — CONTENT — PREFILING PROCEDURES. (1) Each transmission utility seeking authority to site electric transmission facilities in a national interest electric transmission corridor, shall submit a notice of intent to file an application for a route certificate. The notice of intent shall be filed with the commission at least […]