Section 61-516 – PRIORITY DESIGNATION FOR ELECTRIC TRANSMISSION PROJECTS.

61-516. PRIORITY DESIGNATION FOR ELECTRIC TRANSMISSION PROJECTS. (1) The legislature finds that the timely review and permitting of electric transmission facilities is critical to the well-being of the citizens and the economy of this state and the region. The legislature further finds that enactment of this section is necessary to promote the public interest. The […]

Section 61-501 – INVESTMENT OF AUTHORITY.

61-501. INVESTMENT OF AUTHORITY. The public utilities commission is hereby vested with power and jurisdiction to supervise and regulate every public utility in the state and to do all things necessary to carry out the spirit and intent of the provisions of this act. History: [(61-501) 1913, ch. 61, sec. 29, p. 248; reen. C.L. […]