14-39-1-10. Disclosure of Pipeline’s Actual Route

Sec. 10. Not later than one hundred eighty (180) days after the completion of a carbon dioxide transmission pipeline for which the department has issued a certificate of authority under this chapter, the carbon dioxide transmission pipeline company shall provide maps and other documentation to the department showing the actual route in Indiana of the […]

14-39-1-1. “Carbon Dioxide”

Sec. 1. As used in this chapter, “carbon dioxide” means a fluid consisting of more than ninety percent (90%) carbon dioxide molecules. As added by P.L.150-2011, SEC.18. Amended by P.L.291-2019, SEC.1.

14-39-1-2. “Carbon Dioxide Transmission Pipeline”

Sec. 2. As used in this chapter, “carbon dioxide transmission pipeline” means the part of a pipeline in Indiana, including appurtenant facilities, property rights, and easements, that is used exclusively for the purpose of transporting carbon dioxide to a carbon management application, including sequestration, enhanced oil recovery, and deep saline injection, within or outside Indiana. […]

14-39-1-2.5. “Underground Storage of Carbon Dioxide”

Sec. 2.5. As used in this chapter, “underground storage of carbon dioxide” means the injection of carbon dioxide into, and storage of carbon dioxide in, underground strata and formations at the site of the carbon sequestration pilot project, as described in section 3.5 of this chapter, pursuant to one (1) or more federal permits issued […]

14-39-1-3.5. Carbon Sequestration Pilot Project

Sec. 3.5. (a) This chapter authorizes the establishment of a carbon sequestration pilot project: (1) that will: (A) capture carbon dioxide at the proposed ammonia plant to be located at 444 West Sanford Avenue, West Terre Haute, Indiana; and (B) inject the carbon dioxide underground through one (1) or more injection wells pursuant to a […]

14-39-1-5. Confidential Information

Sec. 5. (a) Except as provided in subsection (b), if a carbon dioxide transmission pipeline company files with the department a verified certificate stating the reasons that the designation of confidential information is necessary, the carbon dioxide transmission pipeline company may designate information that it submits in an application to the department, or in subsequent […]

14-39-1-6. Issuing a Certificate of Authority

Sec. 6. A certificate of authority issued by the department under this chapter must include at least the following: (1) A grant of authority to construct and operate a carbon dioxide transmission pipeline as requested in the application. (2) A grant of authority to use, occupy, and construct pipeline facilities in any designated public right-of-way […]