14-39-1-3.5. Carbon Sequestration Pilot Project

Sec. 3.5. (a) This chapter authorizes the establishment of a carbon sequestration pilot project: (1) that will: (A) capture carbon dioxide at the proposed ammonia plant to be located at 444 West Sanford Avenue, West Terre Haute, Indiana; and (B) inject the carbon dioxide underground through one (1) or more injection wells pursuant to a […]

14-39-1-5. Confidential Information

Sec. 5. (a) Except as provided in subsection (b), if a carbon dioxide transmission pipeline company files with the department a verified certificate stating the reasons that the designation of confidential information is necessary, the carbon dioxide transmission pipeline company may designate information that it submits in an application to the department, or in subsequent […]

14-39-1-6. Issuing a Certificate of Authority

Sec. 6. A certificate of authority issued by the department under this chapter must include at least the following: (1) A grant of authority to construct and operate a carbon dioxide transmission pipeline as requested in the application. (2) A grant of authority to use, occupy, and construct pipeline facilities in any designated public right-of-way […]

14-38-2-17. Entry Onto Land Without Notice or Hearing

Sec. 17. If: (1) an emergency exists; and (2) the department determines that irreparable injury will result unless immediate action is taken; the department may enter or authorize the entry upon the land by order of the department without notice or hearing for the purpose of taking the temporary remedial action that the department considers […]

14-39-1-7. Right of Pipeline Company or Pilot Project Operator to Use Eminent Domain

Sec. 7. (a) If a carbon dioxide transmission pipeline company has received a carbon dioxide transmission pipeline certificate of authority from the department under this chapter and is not able to reach an agreement with a property owner for the construction, operation, and maintenance of the carbon dioxide transmission pipeline on the owner’s property, the […]

14-39-1-8. Applicable Eminent Domain Statutes

Sec. 8. (a) Except as otherwise provided in this chapter, IC 32-24-1 applies to the condemnation of property under section 7(a) of this chapter by a carbon dioxide transmission pipeline company. (b) IC 32-24-5 and (pursuant to IC 32-24-5-5) IC 32-24-1 apply to the condemnation of property under section 7(b) of this chapter by the […]

14-38-2-3. “Plug” or “Plugging” Defined

Sec. 3. As used in this chapter, “plug” or “plugging” means the stopping of the flow or migration of oil, gas, water, or other fluid or material up or down a test hole. [Pre-1995 Recodification Citation: 13-4-5-2(5).] As added by P.L.1-1995, SEC.31.