22-15-3.3-1. “Applicant”
Sec. 1. As used in this chapter, “applicant” means a person who submits an application for a local plan review. As added by P.L.218-2014, SEC.15.
22-15-4-1. Industrialized Building Systems; Qualification for Certification; Seal; Exemption
Sec. 1. (a) The department shall certify an industrialized building system for use in Indiana to an applicant who qualifies under this section. If an applicant qualifies for certification under this section, the department shall provide the applicant with a seal for the certified industrial building system. (b) To qualify for a certification under this […]
22-15-3.2-8. Receipt of Application; Notice of Design Release Issuance or Plan Review
Sec. 8. Upon receiving a complete application for a design release, the department shall do one (1) of the following: (1) Not later than ten (10) business days after the application is received, send written notice to the applicant that a design release will be issued. Not later than the next business day after the […]
22-15-3.3-2. “Application”
Sec. 2. As used in this chapter, “application” means an application for a local plan review and any supporting plans and specifications. As added by P.L.218-2014, SEC.15.
22-15-4-2. Mobile Structures; Qualification for Certification; Seal; Exemption
Sec. 2. (a) The department shall certify a mobile structure for sale and use in Indiana for an applicant who qualifies under this section. If an applicant qualifies for certification under this section, the department shall provide the applicant with a seal for the certified mobile structure. (b) To qualify for certification under this section, […]
22-15-3.2-9. Notice of Plan Approval and Design Release; Notice That Plan Corrections Required
Sec. 9. If the department sends an applicant notice of a plan review under section 8(2) of this chapter within the period required, the department shall do one (1) of the following: (1) Not later than twenty (20) business days after the date that notice of the plan review is sent, send notice to the […]
22-15-3.3-3. “Construction Activity”
Sec. 3. As used in this chapter, “construction activity” refers to any physical improvements to real property undertaken for the purpose of constructing a Class 1 structure that is subject to a local plan review. As added by P.L.218-2014, SEC.15.
22-15-4-3. Inspections and Certifications; Authorization
Sec. 3. The commission may authorize any qualified person to conduct inspections and issue certifications under this chapter. As added by P.L.245-1987, SEC.4.
22-15-3.2-10. Receipt of Plan Corrections; Notice of Plan Approval and Design Release; Notice That Additional Plans Corrections Required
Sec. 10. (a) If the department receives corrections to a plan in response to a notice sent under section 9(2) of this chapter, and any time the department receives corrections to a notice under subdivision (2) thereafter, the department shall do one (1) of the following: (1) Not later than ten (10) business days after […]
22-15-3.3-4. “Unit”
Sec. 4. As used in this chapter, “unit” means a county, city, or town. As added by P.L.218-2014, SEC.15.