5-32-3-6. Contract Negotiation With Selected Offeror

Sec. 6. If the public agency determines to proceed with the project, the public agency shall enter into negotiations with the offeror whose proposal has been selected by the evaluation committee considering: (1) the responses to the RFP; (2) any interviews with selected offerors; and (3) evaluation of fees. As added by P.L.128-2014, SEC.1.

5-32-3-7. Cmc Performance of Work

Sec. 7. A CMc may perform a part of the work only if: (1) the public agency approves of the CMc’s performance of the work; (2) the CMc would be awarded a contract for the work under the applicable contract award standard; and (3) the CMc performs only such work that equals not more than […]

5-32-4-1. Negotiation of Cmc Contract Terms and Conditions

Sec. 1. After the public agency has selected an offeror to be the CMc, the public agency and that offeror may negotiate the final terms and conditions of the contract for CMc services for the project. As added by P.L.128-2014, SEC.1.

5-32-2-11. “Gmp”

Sec. 11. “GMP” refers to the guaranteed maximum price for the work as may be established in the CMc contract. As added by P.L.128-2014, SEC.1.

5-32-2-12. “Offeror”

Sec. 12. “Offeror” refers to a person who submits a response to an RFP. As added by P.L.128-2014, SEC.1.