5-32-3-6. Contract Negotiation With Selected Offeror
Sec. 6. If the public agency determines to proceed with the project, the public agency shall enter into negotiations with the offeror whose proposal has been selected by the evaluation committee considering: (1) the responses to the RFP; (2) any interviews with selected offerors; and (3) evaluation of fees. As added by P.L.128-2014, SEC.1.
5-32-3-7. Cmc Performance of Work
Sec. 7. A CMc may perform a part of the work only if: (1) the public agency approves of the CMc’s performance of the work; (2) the CMc would be awarded a contract for the work under the applicable contract award standard; and (3) the CMc performs only such work that equals not more than […]
5-32-4-1. Negotiation of Cmc Contract Terms and Conditions
Sec. 1. After the public agency has selected an offeror to be the CMc, the public agency and that offeror may negotiate the final terms and conditions of the contract for CMc services for the project. As added by P.L.128-2014, SEC.1.
5-32-4-2. Cmc to Provide Payment and Performance Bonds; Construction May Not Proceed Without Bonds
Sec. 2. (a) Subject to this article, the CMc contract must require the CMc to provide payment and performance bonds in an amount not less than the estimated construction costs of the project or the GMP, as provided by the RFP. (b) Construction may not be performed until the CMc has provided the bonds for […]
5-32-2-10. “First Tier Subcontractor”
Sec. 10. “First tier subcontractor” refers to a subcontractor who contracts directly with the CMc. As added by P.L.128-2014, SEC.1.
5-32-4-3. Contract Provisions; Adjustment of Compensation, Other Incentives
Sec. 3. A CMc contract must describe the details of any adjustment of compensation or other incentives negotiated between the public agency and the CMc. As added by P.L.128-2014, SEC.1.
5-32-2-11. “Gmp”
Sec. 11. “GMP” refers to the guaranteed maximum price for the work as may be established in the CMc contract. As added by P.L.128-2014, SEC.1.
5-32-4-4. Cost Overrun or Delay Damages; Early Completion Incentives
Sec. 4. A CMc contract may describe whether the CMc and the public agency agree to any cost overrun or delay damages or early completion incentives. As added by P.L.128-2014, SEC.1.
5-32-2-12. “Offeror”
Sec. 12. “Offeror” refers to a person who submits a response to an RFP. As added by P.L.128-2014, SEC.1.
5-32-4-5. Changes to Cmc Contract
Sec. 5. Changes in the contract for CMc services may be made as provided in the CMc contract. As added by P.L.128-2014, SEC.1.