Section 479.12 – Final order — condition.
479.12 Final order — condition. The board may grant a permit in whole or in part upon terms, conditions, and restrictions as to safety requirements and as to location and route as determined by it to be just and proper. Before a permit is granted to a pipeline company, the board, after a public hearing […]
Section 479.13 – Costs and fees.
479.13 Costs and fees. The applicant shall pay all costs of the informational meetings, hearing, and necessary preliminary investigation including the cost of publishing notice of hearing, and shall pay the actual unrecovered costs directly attributable to construction inspections conducted by the board or the board’s designee. [C31, §8338-d11, -d12; C35, §8338-f26; C39, §8338.34; C46, […]
Section 479.14 – Inspection fee.
479.14 Inspection fee. The board may, in accordance with section 476.10, charge a pipeline company with an annual inspection fee that is directly attributable to the costs of conducting annual inspections pursuant to this chapter. [C31, §8338-d13; C35, §8338-f27; C39, §8338.35; C46, 50, 54, 58, 62, 66, 71, 73, 75, §490.14; C77, 79, 81, §479.14] […]
Section 479.15 – Failure to pay.
479.15 Failure to pay. It shall be the duty of the board to collect all inspection fees provided in this chapter, and failure to pay any such inspection fee within thirty days after the time the same shall become due shall be cause for revocation of the permit. [C35, §8338-f28; C39, §8338.36; C46, 50, 54, […]
Section 479.16 – Receipt of funds.
479.16 Receipt of funds. All moneys received under this chapter shall be remitted monthly to the treasurer of state and credited to the department of commerce revolving fund created in section 546.12 as provided in section 476.10. [C31, §8338-d14; C35, §8338-f29, -f30; C39, §8338.37, 8338.38; C46, 50, 54, 58, 62, 66, 71, §490.16, 490.17; C73, […]
Section 479.17 – Rules.
479.17 Rules. The said board shall have full authority and power to promulgate such rules as it deems proper and expedient to insure the orderly conduct of the hearings herein provided for and also to prescribe rules for the enforcement of this chapter. [C31, §8338-d15; C35, §8338-f31; C39, §8338.39; C46, 50, 54, 58, 62, 66, […]
Section 479.18 – Permit.
479.18 Permit. The board shall prepare and issue any permit granted in accordance with section 479.12. Said permit shall show the name and address of the pipeline company to which it is issued and identify by reference thereto the decision and order of the board under which said permit is issued. It shall be signed […]
Section 479.19 – Limitation on grant.
479.19 Limitation on grant. No exclusive right shall ever be granted to any pipeline company to construct, maintain, and operate its pipeline or lines along, over or across any public highway, grounds or waters and no such permit shall ever be granted for a longer period than twenty-five years. [C31, §8338-d17; C35, §8338-f33; C39, §8338.41; […]
Section 479.20 – Sale of permit.
479.20 Sale of permit. No permit shall be sold until the sale is approved by the board. [C35, §8338-f34; C39, §8338.42; C46, 50, 54, 58, 62, 66, 71, 73, 75, §490.21; C77, 79, 81, §479.20]
Section 479.5 – Application for permit.
479.5 Application for permit. 1. A pipeline company doing business in this state shall file with the board its verified petition asking for a permit to construct, maintain and operate its pipeline or lines along, over or across the public or private highways, grounds, waters and streams of any kind of this state. Any pipeline […]