Section 460.1337 – Payment of Electricity to Operate Small Cell Wireless Facility.
460.1337 Payment of electricity to operate small cell wireless facility. Sec. 37. A wireless provider is responsible for arranging and paying for the electricity used to operate a small cell wireless facility. History: 2018, Act 365, Eff. Mar. 12, 2019
Section 460.1339 – Scope of Act; Application to and Effect on Certain Electric Utilities.
460.1339 Scope of act; application to and effect on certain electric utilities. Sec. 39. (1) This act does not add to, replace, or supersede any law regarding poles or conduits, similar structures, or equipment of any type owned or controlled by an investor-owned utility whose rates are regulated by the MPSC, an affiliated transmission company, […]
Section 460.1319 – Authority Poles; Exclusive Arrangement Prohibited; Limitation on Rates, Fees, and Terms; Elimination of Aboveground Poles.
460.1319 Authority poles; exclusive arrangement prohibited; limitation on rates, fees, and terms; elimination of aboveground poles. Sec. 19. (1) An authority shall not enter into an exclusive arrangement with any person for the right to attach to authority poles. A person who purchases, controls, or otherwise acquires an authority pole is subject to the requirements […]
Section 460.1321 – Municipally Owned Electric Utility; Collocation on Nonauthority Poles; Standards; Application Process; Moratorium Prohibited; Rates; Make-Ready Work.
460.1321 Municipally owned electric utility; collocation on nonauthority poles; standards; application process; moratorium prohibited; rates; make-ready work. Sec. 21. (1) The governing body of a municipally owned electric utility shall not enter into an exclusive arrangement with any person for the right to attach to nonauthority poles. (2) The governing body of a municipally owned […]
Section 460.1323 – Attaching Entity; Standards; Compliance; Rate; Civil Action.
460.1323 Attaching entity; standards; compliance; rate; civil action. Sec. 23. (1) An attaching entity, and all contractors or parties under its control, shall comply with reliability, safety, and engineering standards adopted by the governing body of a municipally owned electric utility, including, but not limited to, the following: (a) Applicable engineering and safety standards governing […]
Section 460.1325 – Jurisdiction; Authority; Certain Interior Structures, Campuses, Stadiums, and Athletic Facilities.
460.1325 Jurisdiction; authority; certain interior structures, campuses, stadiums, and athletic facilities. Sec. 25. An authority does not have jurisdiction or authority over the design, engineering, construction, installation, or operation of a small cell wireless facility located in an interior structure or upon a campus of an institution of higher education including any stadiums or athletic […]
Section 460.1327 – Circuit Courts; Jurisdiction; Right to Appeal.
460.1327 Circuit courts; jurisdiction; right to appeal. Sec. 27. The circuit court has jurisdiction to determine all disputes arising under this act. Venue lies in the judicial circuit where the authority or municipally owned electric utility is located. In addition to its right to appeal to the circuit court, an applicant may elect, at its […]
Section 460.1329 – Indemnification; Insurance Requirements.
460.1329 Indemnification; insurance requirements. Sec. 29. As part of the permit process under section 15, a zoning approval process under section 17, or a request process under section 21, an authority or the governing body of a municipally owned electric utility may require a wireless provider to do the following with respect to a small […]
Section 460.1331 – Fee and Rate Limitations.
460.1331 Fee and rate limitations. Sec. 31. An authority may establish a fee or rate less than the maximum specified in section 13(3), 15(3), 17(4), or 19(2), subject to other requirements of this act. History: 2018, Act 365, Eff. Mar. 12, 2019
Section 460.1333 – Bonding Requirements; Limitations.
460.1333 Bonding requirements; limitations. Sec. 33. (1) As a condition of a permit described in this act, an authority may adopt bonding requirements for small cell wireless facilities if both of the following requirements are met: (a) The authority imposes similar requirements in connection with permits issued for similarly situated users of the ROW. (b) […]