Section 16C.33 — Design-build.
16C.33 DESIGN-BUILD. Subdivision 1. Conflict of interest. A board member may not participate in the review, discussion, or selection of a primary designer, a design-builder, or a firm in which the member has a financial interest. Subd. 2. Design-builder licensing requirements. (a) Each design-builder must be, employ, or have as a partner, member, coventurer, or […]
Section 16C.34 — Construction Manager At Risk.
16C.34 CONSTRUCTION MANAGER AT RISK. Subdivision 1. Solicitation of qualifications. (a) Every user agency, except the Capitol Area Architectural and Planning Board, shall submit a written request for proposals for a construction manager at risk for its project to the commissioner. The written request for proposals must include a description of the project, the estimated […]
Section 16C.35 — Job Order Contracting.
16C.35 JOB ORDER CONTRACTING. Subdivision 1. Authority. The commissioner may undertake construction utilizing job order contracting for projects that do not exceed a construction cost of $250,000. Subd. 2. Job order contracting request for qualifications. (a) The commissioner is authorized to issue a request for qualifications that includes the criteria that will be used for […]
Section 16C.36 — Reorganization Services Under Master Contract.
16C.36 REORGANIZATION SERVICES UNDER MASTER CONTRACT. The commissioner of administration must make available under a master contract program a list of eligible contractors who can assist state agencies in using data analytics to: (1) accomplish agency reorganization along service rather than functional lines in order to provide more efficient and effective service; and (2) bring […]
Section 16C.25 — Building And Construction Contracts.
16C.25 BUILDING AND CONSTRUCTION CONTRACTS. Notwithstanding sections 16C.06 and 16C.10, sections 16C.251 to 16C.29, and other provisions of law not inconsistent with the provisions of sections 16C.251 to 16C.29, apply to building and construction contracts entered into on or after August 1, 2002. History: 1998 c 386 art 1 s 26; 2002 c 254 s […]
Section 16C.251 — Best And Final Offer.
16C.251 BEST AND FINAL OFFER. A “best and final offer” solicitation process may not be used for building and construction contracts. History: 2007 c 148 art 2 s 44
Section 16C.26 — Competitive Bids Or Proposals.
16C.26 COMPETITIVE BIDS OR PROPOSALS. Subdivision 1. Application. Except as otherwise provided by section 16C.10 and this section, all contracts for building and construction or repairs must be based on competitive bids or proposals. “Competitive proposals” specifically refers to the method of procurement described in section 16C.28, subdivision 1, paragraph (a), clause (2), and paragraph […]
Section 16C.28 — Contracts; Award.
16C.28 CONTRACTS; AWARD. Subdivision 1. Award requirements. (a) All state building and construction contracts entered into by or under the supervision of the commissioner or an agency for which competitive bids or proposals are required may be awarded to either of the following: (1) the lowest responsible bidder, taking into consideration conformity with the specifications, […]
Section 16C.281 — Original Jurisdiction Of Public Procurement Actions.
16C.281 ORIGINAL JURISDICTION OF PUBLIC PROCUREMENT ACTIONS. Subdivision 1. Original jurisdiction. (a) Original jurisdiction is granted to the district court over any action seeking legal, equitable, or declaratory relief arising under or based upon the alleged violation of any law governing public procurement requirements, public procurement procedures, or the award of any public contract. (b) […]
Section 16C.285 — Responsible Contractor Requirement Defined.
16C.285 RESPONSIBLE CONTRACTOR REQUIREMENT DEFINED. Subdivision 1. Definitions. (a) For purposes of this section, the terms defined in this subdivision have the meanings given them. (b) “Construction contract” means a contract or subcontract of any tier for work on a project. (c) “Contractor” means a prime contractor or subcontractor or motor carrier, and does not […]