Section 374.12 — Plans And Specifications Drawn.
374.12 PLANS AND SPECIFICATIONS DRAWN. Either before or after the selection of the building site, the commission shall have plans and specifications for the building prepared and may employ architects, engineers, drafters, and clerical help to prepare the plans and specifications. The commission shall set the compensation of the employees. The city and the county […]
Section 374.13 — To Advertise For Bids.
374.13 TO ADVERTISE FOR BIDS. Subdivision 1. Bidding process. When the plans and specifications are completed and approved by the city council and the county board, the commission shall, after notice appropriate to inform possible bidders, obtain bids or proposals for all or any portion of the work or materials, or both, to be done, […]
Section 374.14 — Certified Checks With All Bids.
374.14 CERTIFIED CHECKS WITH ALL BIDS. Each person submitting bids or proposals under section 374.13 shall file with the bid or proposal a certified check in an amount prescribed in the specifications of the commission for the building, to be retained as liquidated damages and divided equally between the city and county in case of […]
Section 374.15 — Wages.
374.15 WAGES. Work specifications shall contain a provision that skilled and unskilled laborers employed in the work shall be paid the wage required to be paid by contractors doing work for the city, if the city has an ordinance providing a scale of wages. History: (643-15) 1929 c 397 s 15; 1985 c 109 s […]
Section 374.16 — Cost Of Removing And Remodeling.
374.16 COST OF REMOVING AND REMODELING. If the selected site is occupied by an existing city hall and courthouse, and temporary quarters must be provided for officers and officials before completion of the new building, the cost of remodeling temporary quarters and moving expenses shall be considered part of the cost of the new building. […]
Section 374.17 — Commission May Appoint Architects.
374.17 COMMISSION MAY APPOINT ARCHITECTS. The work of constructing, equipping, and furnishing the building shall be conducted and completed under the direction and supervision of the commission. The commission members are charged with the duty of requiring that the work is done in accordance with the plans and specifications. The commission may employ architects, engineers, […]
Section 374.18 — Management Of Building.
374.18 MANAGEMENT OF BUILDING. If the county and city jointly own and operate a city hall and courthouse building when a new building is constructed, the same persons or committees that managed the old building shall manage the new building. In all other cases, a joint committee consisting of two members of the county board […]
Section 374.001 — Do Not Apply To Ramsey Or Hennepin County.
374.001 DO NOT APPLY TO RAMSEY OR HENNEPIN COUNTY. Sections 374.01 to 374.21 do not apply to Ramsey or Hennepin County. History: 1974 c 435 art 7 s 1; 1979 c 198 art 4 s 13
Section 374.01 — County And City Of First Class May Build Courthouse.
374.01 COUNTY AND CITY OF FIRST CLASS MAY BUILD COURTHOUSE. Any county having within its limits a city of the first class may, together with the city, jointly acquire land for, construct, equip, furnish, maintain, and operate a joint courthouse and city hall building. History: (643-1) 1929 c 397 s 1; 1985 c 109 s […]
Section 374.02 — Expense Divided.
374.02 EXPENSE DIVIDED. The county and city shall share equally in the cost of acquiring land for constructing, equipping, and furnishing the building. The building shall not be constructed or contracted to be constructed, no land shall be acquired, and no bonds shall be issued or sold by the county until the city has been […]