18-2-403. Preference of Montana labor in public works — wages — tax-exempt project — federal exception
18-2-403. Preference of Montana labor in public works — wages — tax-exempt project — federal exception. (1) In every public works contract, there must be inserted in the bid specification and the public works contract a provision requiring the contractor to give preference to the employment of bona fide Montana residents in the performance of the […]
18-2-419. Zone pay and per diem
18-2-419. Zone pay and per diem. If there is not sufficient data reported to establish zone pay or per diem for a trade classification, the department may establish a zone pay or a per diem amount that reasonably approximates an applicable average zone pay or per diem rate that is payable for the trade classification. History: En. […]
18-2-404. Approval of public works contract — bond
18-2-404. Approval of public works contract — bond. (1) All public works contracts under this part must be approved in writing by the legal adviser of the contracting county, municipal corporation, school district, assessment district, or special improvement district body or officer prior to execution by the contracting public officer or officers. (2) In all public works […]
18-2-420. reserved
18-2-420 reserved.
18-2-405. Repealed
18-2-405. Repealed. Sec. 8, Ch. 609, L. 1993. History: En. Sec. 1, Ch. 102, L. 1931; re-en. Sec. 3043.1, R.C.M. 1935; amd. Sec. 1, Ch. 32, L. 1955; amd. Sec. 1, Ch. 43, L. 1961; amd. Sec. 1, Ch. 265, L. 1969; amd. Sec. 1, Ch. 375, L. 1973; amd. Sec. 1, Ch. 531, L. 1975; R.C.M. […]
18-2-421. Notice
18-2-421. Notice. When a public works project is accepted by the public contracting agency, a notice of acceptance and the completion date of the project must be sent to the department. However, in the case of public works contracts that amount to $50,000 or less in cost, the notice of acceptance and the completion date of […]
18-2-406. Posting wage scale and fringe benefits
18-2-406. Posting wage scale and fringe benefits. The contractor performing work or providing construction services under public works contracts, as provided in this part, shall post in a prominent and accessible site on the project or staging area, not later than the first day of work and continuing for the entire duration of the project, a […]
18-2-407. Forfeiture for failure to pay standard prevailing rate of wages
18-2-407. Forfeiture for failure to pay standard prevailing rate of wages. (1) Except as provided in 18-2-403, a contractor, subcontractor, or employer who pays workers or employees at less than the standard prevailing rate of wages as established under the public works contract shall forfeit to the department a penalty at a rate of up to […]
18-2-408. Renumbered 18-2-432
18-2-408. Renumbered 18-2-432. Code Commissioner, 1985.
18-2-409. Montana residents to be employed on state construction contracts
18-2-409. Montana residents to be employed on state construction contracts. (1) On any state construction project funded by state or federal funds, except a project partially funded with federal aid money from the United States department of transportation or when residency preference laws are specifically prohibited by federal law and to which the state is a […]