75-20-216. Study, evaluation, and report on proposed facility — assistance by other agencies

75-20-216. Study, evaluation, and report on proposed facility — assistance by other agencies. (1) After receipt of an application, the department shall within 30 days notify the applicant in writing that: (a) the application is in compliance and is accepted as complete; or (b) the application is not in compliance and shall list the deficiencies. Upon correction of […]

75-20-217. Voiding an application

75-20-217. Voiding an application. An application may be voided by the department following notice and an opportunity for hearing for: (1) any material and knowingly false statement in the application or in accompanying statements or studies required of the applicant; (2) failure to file an application in substantially the form and content required by this chapter and the […]

75-20-218. Repealed

75-20-218. Repealed. Sec. 24, Ch. 329, L. 1997. History: En. Sec. 7, Ch. 327, L. 1973; amd. Sec. 3, Ch. 268, L. 1974; amd. Sec. 39, Ch. 213, L. 1975; amd. Sec. 7, Ch. 494, L. 1975; R.C.M. 1947, 70-807(4); amd. Sec. 10, Ch. 676, L. 1979; amd. Sec. 5, Ch. 539, L. 1981; amd. Sec. 10, […]

75-20-219. Amendments to certificate

75-20-219. Amendments to certificate. (1) (a) Except as provided in 75-20-228, within 30 days after notice of an amendment to a certificate is given as set forth in 75-20-213(1), including notice to all active parties to the original proceeding, the department shall determine whether the proposed change in the facility would result in a material increase […]

75-20-220. Repealed

75-20-220. Repealed. Sec. 24, Ch. 329, L. 1997. History: En. Sec. 9, Ch. 327, L. 1973; amd. Sec. 9, Ch. 494, L. 1975; R.C.M. 1947, 70-809(3); amd. Sec. 12, Ch. 676, L. 1979; amd. Sec. 6, Ch. 539, L. 1981; amd. Sec. 223, Ch. 418, L. 1995; amd. Sec. 6, Ch. 583, L. 1995.

75-20-205. Repealed

75-20-205. Repealed. Sec. 24, Ch. 329, L. 1997. History: En. Sec. 4, Ch. 591, L. 1985; amd. Sec. 1, Ch. 246, L. 1987; amd. Sec. 215, Ch. 418, L. 1995; amd. Sec. 536, Ch. 546, L. 1995.

75-20-207. Notice requirement for certain electric transmission lines

75-20-207. Notice requirement for certain electric transmission lines. Whenever a person plans to construct an electric transmission line or associated facilities under the provisions of 75-20-104(10)(a)(ii), it must provide public notice to persons residing in the area in which any portion of the electric transmission facility may be located and to the department. This notice must […]

75-20-208. Certain electric transmission lines — verification of requirements

75-20-208. Certain electric transmission lines — verification of requirements. (1) Prior to constructing a transmission line under 75-20-104(10)(a)(ii), the person planning to construct the line shall provide to the department within 36 months of the date of the public notice provided under 75-20-207, unless extended by the department for good cause: (a) copies of the right-of-way agreements […]