75-20-207. Notice requirement for certain electric transmission lines

75-20-207. Notice requirement for certain electric transmission lines. Whenever a person plans to construct an electric transmission line or associated facilities under the provisions of 75-20-104(10)(a)(ii), it must provide public notice to persons residing in the area in which any portion of the electric transmission facility may be located and to the department. This notice must […]

75-20-208. Certain electric transmission lines — verification of requirements

75-20-208. Certain electric transmission lines — verification of requirements. (1) Prior to constructing a transmission line under 75-20-104(10)(a)(ii), the person planning to construct the line shall provide to the department within 36 months of the date of the public notice provided under 75-20-207, unless extended by the department for good cause: (a) copies of the right-of-way agreements […]

75-20-211. Application — filing and contents — proof of service and notice

75-20-211. Application — filing and contents — proof of service and notice. (1) (a) An applicant shall file with the department an application for a certificate under this chapter and for the permits required under the laws administered by the department in the form that is required under applicable rules, containing the following information: (i) a description […]

75-20-212. Cure for failure of service

75-20-212. Cure for failure of service. Inadvertent failure of service on or notice to any of the municipalities, government agencies, or persons identified in 75-20-211 may be cured pursuant to orders of the department designed to afford them adequate notice to enable their effective participation in the proceeding. History: En. Sec. 6, Ch. 327, L. 1973; amd. […]

75-20-201. Certificate required — operation in conformance — certificate for nuclear facility — applicability to federal facilities

75-20-201. Certificate required — operation in conformance — certificate for nuclear facility — applicability to federal facilities. (1) Except for a facility under diligent onsite physical construction or in operation on January 1, 1973, a person may not commence to construct a facility in the state without first applying for and obtaining a certificate of compliance […]

75-20-202. Repealed

75-20-202. Repealed. Sec. 24, Ch. 329, L. 1997. History: En. Sec. 4, Ch. 327, L. 1973; amd. Sec. 4, Ch. 494, L. 1975; R.C.M. 1947, 70-804(3) thru (5); amd. Sec. 3, I.M. 80, app. Nov. 7, 1978; amd. Sec. 2, Ch. 539, L. 1981; amd. Sec. 2, Ch. 167, L. 1983; amd. Sec. 9, Ch. 573, L. […]

75-20-203. Certificate transferable

75-20-203. Certificate transferable. A certificate may be transferred to a person who agrees to comply with the terms, conditions, and modifications contained in the certificate. History: En. Sec. 4, Ch. 327, L. 1973; amd. Sec. 4, Ch. 494, L. 1975; R.C.M. 1947, 70-804(2); amd. Sec. 3, I.M. 80, app. Nov. 7, 1978; amd. Sec. 3, Ch. 676, […]

75-20-204. Facilities subject to federal energy regulatory commission jurisdiction

75-20-204. Facilities subject to federal energy regulatory commission jurisdiction. (1) For a facility that is subject to the jurisdiction of the federal energy regulatory commission, the department shall file a state recommendation with the commission. (2) A person making application to the federal energy regulatory commission shall file with the department notice of and a copy of […]