39-2820 – Contracting agency; cost estimate; conduct contract negotiations.
39-2820. Contracting agency; cost estimate; conduct contract negotiations. (1) Before the construction manager begins any construction services, a contracting agency shall: (a) Conduct an independent cost estimate for the project; and (b) Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services. (2) If the construction manager and […]
39-2821 – Contracts; changes authorized.
39-2821. Contracts; changes authorized. A design-build contract, a progressive design-build contract, and a construction manager-general contractor contract may be conditioned upon later refinements in scope and price and may permit the contracting agency in agreement with the design-builder, progressive design-builder, or construction manager to make changes in the project without invalidating the contract. Source Laws […]
39-2822 – Department; authority for political subdivision projects.
39-2822. Department; authority for political subdivision projects. The department may enter into agreements under sections 39-2808 to 39-2824 to let, design, and construct projects for political subdivisions when any of the funding for such projects is provided by or through the department. In such instances, the department may enter into contracts with the design-builder, progressive […]
39-2823 – Insurance.
39-2823. Insurance. Nothing in sections 39-2808 to 39-2824 shall limit or reduce statutory or regulatory requirements regarding insurance. Source Laws 2016, LB960, § 23; Laws 2019, LB583, § 17.
39-2824 – Rules and regulations.
39-2824. Rules and regulations. The department may adopt and promulgate rules and regulations to carry out the Transportation Innovation Act. An eligible county, a city of the metropolitan class, or a city of the primary class may adopt a resolution or an ordinance establishing rules to carry out the act. Source Laws 2016, LB960, § […]
39-2825 – Public-private partnership delivery method; authorized.
39-2825. Public-private partnership delivery method; authorized. (1) A public-private partnership delivery method may be used for projects under the Transportation Innovation Act as provided in this section and rules and regulations adopted and promulgated pursuant to this section only to the extent allowed under the Constitution of Nebraska. State contracts using this method shall be […]
39-2812 – Process; provisions applicable.
39-2812. Process; provisions applicable. (1) The process for selecting a design-builder and entering into a design-build contract shall be in accordance with sections 39-2813 to 39-2816. (2) Except as otherwise specifically provided in the Transportation Innovation Act, the process for selecting a progressive design-builder and entering into a progressive design-build contract shall be in accordance […]
39-2813 – Request for qualifications for design-build proposals and progressive design-build proposals; publication; short list created.
39-2813. Request for qualifications for design-build proposals and progressive design-build proposals; publication; short list created. (1) A contracting agency shall prepare a request for qualifications for design-build and progressive design-build proposals and shall prequalify design-builders and progressive design-builders. The request for qualifications shall describe the project in sufficient detail to permit a design-builder or a […]
39-2814 – Request for proposals for design-build or progressive design-build contract; elements.
39-2814. Request for proposals for design-build or progressive design-build contract; elements. A contracting agency shall prepare a request for proposals for each design-build or progressive design-build contract. The request for proposals shall contain, at a minimum, the following elements: (1) The guidelines adopted in accordance with section 39-2811. The identification of a publicly accessible location […]
39-2815 – Stipend.
39-2815. Stipend. The contracting agency shall pay a stipend to qualified design-builders that submit responsive proposals but are not selected. Payment of the stipend shall give the contracting agency ownership of the intellectual property contained in the proposals and alternative technical concepts. The amount of the stipend shall be at the discretion of the contracting […]