39-2812 – Process; provisions applicable.

39-2812. Process; provisions applicable. (1) The process for selecting a design-builder and entering into a design-build contract shall be in accordance with sections 39-2813 to 39-2816. (2) Except as otherwise specifically provided in the Transportation Innovation Act, the process for selecting a progressive design-builder and entering into a progressive design-build contract shall be in accordance […]

39-2813 – Request for qualifications for design-build proposals and progressive design-build proposals; publication; short list created.

39-2813. Request for qualifications for design-build proposals and progressive design-build proposals; publication; short list created. (1) A contracting agency shall prepare a request for qualifications for design-build and progressive design-build proposals and shall prequalify design-builders and progressive design-builders. The request for qualifications shall describe the project in sufficient detail to permit a design-builder or a […]

39-2814 – Request for proposals for design-build or progressive design-build contract; elements.

39-2814. Request for proposals for design-build or progressive design-build contract; elements. A contracting agency shall prepare a request for proposals for each design-build or progressive design-build contract. The request for proposals shall contain, at a minimum, the following elements: (1) The guidelines adopted in accordance with section 39-2811. The identification of a publicly accessible location […]

39-2815 – Stipend.

39-2815. Stipend. The contracting agency shall pay a stipend to qualified design-builders that submit responsive proposals but are not selected. Payment of the stipend shall give the contracting agency ownership of the intellectual property contained in the proposals and alternative technical concepts. The amount of the stipend shall be at the discretion of the contracting […]

39-2816 – Submission of proposals; sealed; rank of design-builders and progressive design-builders; negotiation of contract.

39-2816. Submission of proposals; sealed; rank of design-builders and progressive design-builders; negotiation of contract. (1) Design-builders and progressive design-builders shall submit proposals as required by the request for proposals. A contracting agency may meet with individual design-builders and progressive design-builders prior to the time of submitting the proposal and may have discussions concerning alternative technical […]

39-2817 – Selection of construction manager; construction manager-general contractor contract; sections applicable; request for qualifications; prequalification; publication; short list created.

39-2817. Selection of construction manager; construction manager-general contractor contract; sections applicable; request for qualifications; prequalification; publication; short list created. (1) The process for selecting a construction manager and entering into a construction manager-general contractor contract shall be in accordance with this section and sections 39-2818 to 39-2820. (2) A contracting agency shall prepare a request […]

39-2818 – Request for proposals for construction manager-general contractor contract; elements.

39-2818. Request for proposals for construction manager-general contractor contract; elements. A contracting agency shall prepare a request for proposals for each construction manager-general contractor contract. The request for proposals shall contain, at a minimum, the following elements: (1) The guidelines adopted in accordance with section 39-2811. The identification of a publicly accessible location of the […]

39-2820 – Contracting agency; cost estimate; conduct contract negotiations.

39-2820. Contracting agency; cost estimate; conduct contract negotiations. (1) Before the construction manager begins any construction services, a contracting agency shall: (a) Conduct an independent cost estimate for the project; and (b) Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services. (2) If the construction manager and […]

39-2821 – Contracts; changes authorized.

39-2821. Contracts; changes authorized. A design-build contract, a progressive design-build contract, and a construction manager-general contractor contract may be conditioned upon later refinements in scope and price and may permit the contracting agency in agreement with the design-builder, progressive design-builder, or construction manager to make changes in the project without invalidating the contract. Source Laws […]