NRS 338.1697 – Authorized provision in contract with construction manager at risk for construction of public work or portion thereof for guaranteed maximum price.
A contract entered into pursuant to NRS 338.1696 that is for a guaranteed maximum price may include a provision that authorizes the construction manager at risk to receive all or part of any difference between the guaranteed maximum price set forth in the contract and the actual price of construction of the public work, if […]
NRS 338.1698 – Required and authorized provisions in contract for construction of public work or portion thereof awarded to construction manager at risk.
A contract awarded to a construction manager at risk pursuant to NRS 338.1696: 1. Must comply with the provisions of NRS 338.020 to 338.090, inclusive. 2. Must specify a date by which performance of the work required by the contract must be completed. 3. May set forth the terms by which the construction manager at […]
NRS 338.16985 – Duties and powers of construction manager at risk who enters into contract for construction of public work or portion thereof.
A construction manager at risk who enters into a contract for the construction of a public work pursuant to NRS 338.1696: 1. Is responsible for contracting for the services of any necessary subcontractor, supplier or independent contractor necessary for the construction of the public work and for the performance of and payment to any such […]
NRS 338.16991 – Contract between construction manager at risk and subcontractor to provide labor, materials or equipment on project: Eligibility; procedure for determination of qualification of subcontractor to submit proposal.
1. To be eligible to provide labor, materials or equipment on a public work, the contract for which a public body has entered into with a construction manager at risk pursuant to NRS 338.1696, a subcontractor must be: (a) Licensed pursuant to chapter 624 of NRS; and (b) Qualified pursuant to the provisions of this […]
NRS 338.16995 – Contract between construction manager at risk and subcontractor to provide labor, materials or equipment on project: Authority to enter into; procedure for awarding subcontracts of certain estimated value; substitution of subcontractor on such subcontracts; availability of certain information to applicants and public.
1. If a public body enters into a contract with a construction manager at risk for the construction of a public work pursuant to NRS 338.1696, the construction manager at risk may enter into a subcontract for the provision of labor, materials and equipment necessary for the construction of the public work only as provided […]
NRS 338.1696 – Negotiation of contract for construction of public work or portion thereof with construction manager at risk; awarding of contract if public body unable to negotiate satisfactory contract with construction manager at risk; provision by construction manager at risk of information concerning public work and subcontractors.
1. If a public body enters into a contract with a construction manager at risk for preconstruction services pursuant to NRS 338.1693, after the public body has finalized the design for the public work, or any portion thereof sufficient to determine the provable cost of that portion, the public body shall enter into negotiations with […]
NRS 338.1685 – Declaration of legislative intent.
The Legislature hereby declares that the provisions of NRS 338.1685 to 338.16995, inclusive, relating to contracts involving construction managers at risk: 1. Are intended: (a) To promote public confidence and trust in the contracting and bidding procedures for public works established therein; (b) For the benefit of the public, to promote the philosophy of obtaining […]
NRS 338.169 – Public body authorized to construct public work by selecting and entering into contracts with construction manager at risk; limitations.
1. Subject to the provisions of subsection 2, a public body may construct a public work by: (a) Selecting a construction manager at risk pursuant to the provisions of NRS 338.1691 to 338.1696, inclusive; and (b) Entering into separate contracts with a construction manager at risk: (1) For preconstruction services, including, without limitation: (I) Assisting […]
NRS 338.1691 – Qualifications for construction manager at risk.
To qualify to enter into contracts with a public body for preconstruction services and to construct a public work, a construction manager at risk must: 1. Not have been found liable for breach of contract with respect to a previous project, other than a breach for legitimate cause, during the 5 years immediately preceding the […]
NRS 338.1692 – Advertising for proposals for construction manager at risk; contents of request for proposals; requirements for proposals; availability of names of applicants; substitution of employees.
1. A public body or its authorized representative shall advertise for proposals for a construction manager at risk in the manner set forth in paragraph (a) of subsection 1 of NRS 338.1385. 2. A request for proposals published pursuant to subsection 1 must include, without limitation: (a) A description of the public work; (b) An […]