1. A plan for reclamation must provide: (a) That reclamation activities, particularly those relating to the control of erosion, must be conducted simultaneously with the mining operation to the extent practicable, and otherwise must be initiated promptly upon the completion or abandonment of the mining operation in any area that will not be subject to […]
If a mining operation or exploration project is conducted on land administered by a federal agency, an approved federal plan of operations and a surety that are consistent with the requirements of this chapter supersede the requirements for a permit and bond or other surety otherwise required by this chapter. If the mining operation or […]
1. An operator who is required by federal law to file a plan of operation or an amended plan of operation with the United States Bureau of Land Management or the United States Forest Service for operations relating to mining or exploration on public land administered by a federal agency, shall, not later than 30 […]
1. Each operator shall, on or before April 15 of each year, submit to the Administrator a report relating to the status and production of all mining operations and exploration projects in which the operator has engaged and identifying each acre of land affected and land reclaimed by that mining operation or exploration project through […]