156-83. Superintendent of construction. The board of drainage commissioners shall appoint a competent drainage engineer of good repute as superintendent of construction. Such superintendent of construction shall furnish a copy of his monthly and final estimates to the Department of Environmental Quality, in addition to other copies herein provided which shall be filed and preserved. […]
156-84. Letting contracts. The board of drainage commissioners shall cause notice to be given of the letting of the contract. The notice shall be posted at the courthouse door in the county wherein the district was organized. Notice shall be posted no less than 15 days prior to the opening of the bids and shall […]
156-85. Monthly estimates for work and payments thereon; final payment. The superintendent in charge of construction shall make monthly estimates of the amount of work done, and furnish one copy to the contractor and file the other with the secretary of the board of drainage commissioners; and the commissioners shall, within five days after the […]
156-86. Failure of contractors; reletting. If any contractor to whom such work has been let shall fail to perform the same according to the terms specified in his contract, action may be had in behalf of the board of drainage commissioners against such contractor and his bond in the superior court for damages sustained by […]
156-87. Right to enter upon lands; removal of timber. In the construction of the work the contractor shall have the right to enter upon the lands necessary for this purpose and the right to remove private or public bridges or fences and to cross private lands in going to or from the work. In case […]
156-88. Drainage across public or private ways. Where any public ditch, drain or watercourse established under the provisions of this Subchapter crosses or, in the opinion of the board of viewers, should cross a public highway under the supervision of the Department of Transportation the actual cost of constructing the same across the highway shall […]
156-89. Drainage across railroads; procedure. Whenever the engineer and the viewers in charge shall make a survey for the purpose of locating a public levee or drainage district or changing a natural watercourse, and the same would cross the right-of-way of any railroad company, it shall be the duty of the owner in charge of […]
156-90. Notice to railroad. The clerk of the superior court shall have notice served upon the railroad company of the time and place of the meeting to hear and determine the final report of the engineer and viewers, and the railroad company shall have the right to file objections to the report and to appeal […]
156-91. Manner of construction across railroad. (a) Duty of Railroad. – After the contract is let and the actual construction is commenced, if the work is being done with a floating dredge, the superintendent in charge of construction shall notify the railroad company of the probable time at which the contractor will be ready to […]
156-92. Control and repairs by drainage commissioners. Whenever any improvement constructed under this Subchapter is completed it shall be under the control and supervision of the board of drainage commissioners. It shall be the duty of the board to keep the levee, ditch, drain, or watercourse in good repair, and for this purpose they may […]
156-93. Construction of lateral drains. The owner of any land that has been assessed for the cost of the construction of any ditch, drain, or watercourse, as herein provided, shall have the right to use the ditch, drain, or watercourse as an outlet for lateral drains from such land; and if the land be of […]