§22-3-13. General Environmental Protection Performance Standards for Surface Mining; Variances

(a) Any permit issued by the secretary pursuant to this article to conduct surface mining operations shall require that the surface mining operations meet all applicable performance standards of this article and other requirements set forth in legislative rules proposed by the secretary. (b) The following general performance standards are applicable to all surface mines […]

§22-3-13a. Preblast Survey Requirements

(a) At least thirty days prior to commencing blasting, as defined in section twenty-two-a of this article, an operator or an operator’s designee shall make the following notifications in writing to all owners and occupants of man-made dwellings or structures that the operator or operator’s designee will perform preblast surveys in accordance with subsection (e) […]

§22-3-14. General Environmental Protection Performance Standards for the Surface Effects of Underground Mining; Application of Other Provisions of Article to Surface Effects of Underground Mining

(a) The director shall promulgate separate rules directed toward the surface effects of underground coal mining operations, embodying the requirements in subsection (b) of this section: Provided, That in adopting such rules, the director shall consider the distinct difference between surface coal mines and underground coal mines in West Virginia. Such rules may not conflict […]

§22-3-17. Notice of Violation; Procedure and Actions; Enforcement; Permit Revocation and Bond Forfeiture; Civil and Criminal Penalties; Appeals to the Board; Prosecution; Injunctive Relief

(a) If any of the requirements of this article, rules promulgated pursuant thereto or permit conditions have not been complied with, the director shall cause a notice of violation to be served upon the operator or the operator's duly authorized agent. A copy of the notice shall be handed to the operator or the operator's […]

§22-3-18. Approval, Denial, Revision and Prohibition of Permit

(a) Upon the receipt of a complete surface-mining application or significant revision or renewal thereof, including public notification and an opportunity for a public hearing, the director shall grant, require revision of, or deny the application for a permit within sixty days and notify the applicant in writing of the decision. The applicant for a […]

§22-3-19. Permit Revision and Renewal Requirements; Incidental Boundary Revisions; Requirements for Transfer; Assignment and Sale of Permit Rights; Operator Reassignment; and Procedures to Obtain Inactive Status

(a)(1) Any valid permit issued pursuant to this article carries with it the right of successive renewal upon expiration with respect to areas within the boundaries of the existing permit. The holders of the permit may apply for renewal and the renewal shall be issued: Provided, That on application for renewal, the burden is on […]

§22-3-21. Decision of Secretary on Permit Application; Hearing Thereon

(a) If an informal conference has been held, the secretary shall issue and furnish the applicant for a permit and persons who were parties to the informal conference with the written finding granting or denying the permit, in whole or in part, and stating the reasons therefor within sixty days of the informal conference, notwithstanding […]