§54-2-16. Increase or Decrease in Award After Payment Into Court; Costs
When, after such payment into court as is mentioned in section thirteen of this article a subsequent report is made which is confirmed and ordered to be recorded, or the verdict of a jury is found, if the sum ascertained by such subsequent report or verdict exceed what was so paid, and the applicant fail […]
§54-2-16a. Liability for Costs Generally
Except as otherwise specially provided, all costs of a condemnation proceeding in the trial court shall be paid by the applicant. In every condemnation proceeding in an appellate court, costs shall be recovered in such court by the party substantially prevailing.
§54-2-17. Effect of Judgment Against Applicant for Excess
When judgment is rendered against the applicant, pursuant to the preceding section, for any excess ascertained by such subsequent report or verdict, with interest, the applicant shall thereafter have no right to the possession of the land until the judgment is satisfied; but from the time of such satisfaction by the payment of the money […]
§54-2-18. Payment to Clerk; Disposition of Money Paid Into Court; Determination of Conflicting Claims; Notice to Condemnee
Payment of an award or judgment, or any money, under any of the provisions of this chapter may be made to the clerk of the court in which such proceeding is had, and such payment shall be deemed to be a payment into court. Within ten days after the payment of an award, judgment or […]
§54-2-19. Compensation of Commissioners and Jurors
Each commissioner shall receive as compensation for services in each eminent domain proceeding a reasonable amount to be fixed by an order entered of record in the proceeding, said compensation not to exceed the sum of $50 per day to be taxed as a part of the costs of the proceeding. The jurors shall receive […]
§54-2-20. Recordation of Certified Copy of Condemnation Order
When land or an estate or interest therein is taken or appropriated under the provisions of this chapter, the clerk of the court in which such proceeding is had shall, at the cost of the applicant, file and record with the clerk of the county court of each county wherein such land is, a certified […]
§54-2-21. Effective Date of New Percent Interest Rates
The percent interest rate provided for in sections twelve, thirteen, fourteen, fourteen-a, fifteen, sixteen and eighteen of this article, shall be applicable only to condemnation proceedings hereafter instituted. The rate of interest previously applicable to proceedings under the above sections shall continue to be applicable to condemnation proceedings heretofore instituted.
§54-2-11. Setting Aside Report; Recommittal; New Commissioners
If good cause be shown against the report, or if it be defective or erroneous on its face, the court or judge thereof in vacation, as may seem to be proper, may set it aside or recommit it to the same commissioners for further report; or other commissioners may be appointed in the manner hereinbefore […]
§54-2-11a. Waiver of Findings by Commissioners
If at any time prior to the appointment of condemnation commissioners, or in the event condemnation commissioners have been appointed, if at any time prior to the making of a report by the condemnation commissioners pursuant to the provisions of section nine of this article, all of the parties who have appeared in the proceeding […]
§54-2-12. Vesting of Title in Applicant
Except as otherwise provided in this article, at any time within three months after the report, or the verdict of a jury, if there be one, has been confirmed and ordered to be recorded, the sum so ascertained with ten percent interest thereon from the date of the filing of the petition until payment, may […]