Section 41-7-709 – Determination and Apportionment of Cost of Power Portion of Project.
41-7-709. Determination and apportionment of cost of power portion of project. That if any project or amended project includes plans for the generation of electric energy and power, the board of commissioners shall ascertain the total cost of all of the property and works which are necessary to be used in connection with the generation, […]
Section 41-7-703 – Report Made to District Court.
41-7-703. Report made to district court. Upon the adoption of such a resolution, the said commissioners shall file an appropriate report with the district court of the county having jurisdiction of said irrigation district proceeding of the same nature and kind as provided in W.S. 41-7-305 through 41-7-307, for the construction of irrigation works.
Section 41-7-701 – Irrigation Districts May Undertake Power Projects.
41-7-701. Irrigation districts may undertake power projects. Any irrigation district heretofore organized and existing under and by virtue of the provisions of chapter 2, Session Laws of Wyoming, Special Session, 1920, as amended, codified and compiled in W.S. 41-7-101 through 41-7-603 [§§41-7-101 through 41-7-415], as now amended, is hereby authorized and given the power to […]
Section 41-7-702 – Resolution of Commissioners.
41-7-702. Resolution of commissioners. Whenever the commissioners of any duly organized and existing irrigation district, heretofore or hereafter organized under the laws of the state of Wyoming, shall determine by a majority vote thereof that it is and would be beneficial and for the best interest of the landowners and entrymen therein that the development […]
Section 41-7-503 – Petition for Authority to Issue Warrants; Hearing Generally; Decree Generally; Appeal.
41-7-503. Petition for authority to issue warrants; hearing generally; decree generally; appeal. Upon the date set for the hearing of said petition, the judge shall hear evidence in support thereof and in support of any protests or objections properly filed and shall hear and determine all proper issues presented by said petition and any protests […]
Section 41-7-504 – Effect of Decree; Reference to Be Made on Warrants.
41-7-504. Effect of decree; reference to be made on warrants. Said order shall be the authority of the said commissioners and reference shall be made thereto on all warrants issued showing the amount so authorized and the total issued to the time thereof.
Section 41-7-505 – Assessment Roll When Assessments Not Yet Approved or Confirmed; Equalization of Assessments; Levy.
41-7-505. Assessment roll when assessments not yet approved or confirmed; equalization of assessments; levy. It shall be the duty of the commissioners of each irrigation district in which an assessment for benefits and construction has not theretofore been approved or confirmed by the court to prepare an assessment roll of said district which shall contain […]
Section 41-7-601 – Inclusion of Provisions for Maintenance and Reclamation of Injured Lands; Costs.
41-7-601. Inclusion of provisions for maintenance and reclamation of injured lands; costs. The board of commissioners of any irrigation district, in contracting with the United States for the construction, operation and maintenance of its necessary works for the delivery and distribution of water therefrom under the provisions of the federal reclamation act and acts amendatory […]
Section 41-7-602 – Petition for Contract and Assessments; Hearings Generally.
41-7-602. Petition for contract and assessments; hearings generally. Whenever any contract between the United States and an irrigation district so provides, the assessment or assessments for benefits and construction against the individual tracts of land in the district, as now required under W.S. 41-7-401, may be dispensed with, and in such case the board of […]
Section 41-7-603 – Order Approving Contract Deemed Conclusive; Appeal.
41-7-603. Order approving contract deemed conclusive; appeal. The order confirming and approving the proceedings taken to ratify and confirm such contract and the assessment for benefits and construction as provided therein, shall be conclusive as to the regularity of all proceedings relating thereto, unless appealed from within thirty (30) days after the entry of such […]