38-1a-403. Effective time and priority of preconstruction lien — Subordination to bona fide loan.

  • (1) Except as otherwise provided in this chapter, a preconstruction lien:
    • (a) relates back to and takes effect as of the time of filing of the earliest timely filed notice of preconstruction service under Section 38-1a-401 for the anticipated improvement for which the preconstruction lien is claimed; and
    • (b) has priority over:
      • (i) any lien, mortgage, or other encumbrance that attaches after the earliest timely filed notice of preconstruction service is filed; and
      • (ii) any lien, mortgage, or other encumbrance of which the claimant had no notice and that was unrecorded at the time the earliest timely filed notice of preconstruction service is filed.
  • (2) A preconstruction lien is subordinate to an interest securing a bona fide loan if and to the extent that the lien covers preconstruction service provided after the interest securing a bona fide loan is recorded.

Amended by Chapter 464, 2013 General Session