54.270 Conducting monumentation or remonumentation under negotiated contract; cost.

Sec. 10.

(1) Any monumentation or remonumentation conducted under section 8(3) shall be conducted under a negotiated contract. The department shall prepare specifications for each contract negotiated by the department and monitor the field work and notes of work done under each contract to ensure compliance with those specifications.

(2) The department shall pay the cost of any contracts under this section from the fund.

History: 1990, Act 345, Eff. Jan. 1, 1991 ;– Am. 2014, Act 166, Imd. Eff. June 12, 2014