If a contract contains a term that is in conflict with a state standard form contract term or if a standard term is deleted or modified by a term that is not standard, the contract must be reviewed by the Attorney General and approved as to form.
An invitation to bid, a request for proposals, or other solicitation may be cancelled or any or all bids or proposals may be rejected in whole or in part or the date for opening bids or proposals may be delayed when it is in the best interests of the state in accordance with regulations adopted […]
(a) A written determination of nonresponsibility of a bidder or offeror shall be made by the procurement officer in accordance with regulations adopted by the commissioner. The unreasonable failure of a bidder or offeror to promptly supply information in connection with an inquiry with respect to responsibility is grounds for a determination of nonresponsibility with […]
Except for awards made under AS 36.30.170, if the procurement officer awards a contract to a person who does not reside or maintain a place of business in the state and if the supplies, services, professional services, or construction that is the subject of the contract could have been obtained from sources in the state, […]
At least 10 days before the formal award of a contract that is not for construction, and at least five days before the award of a construction contract, under this chapter, except for a contract awarded under AS 36.30.300 – 36.30.320, the procurement officer shall provide to each bidder or offeror notice of intent to […]
Any type of contract that will promote the best interests of the state may be used, except that the use of a cost-plus-a-percentage-of-cost contract is prohibited.
(a) Unless otherwise provided by law, a contract for supplies, services, or professional services may be entered into for any period of time considered to be in the best interests of the state provided the term of the contract and conditions of renewal or extension, if any, are included in the solicitation and funds are […]
(a) Before an award of a contract or a change order or contract modification, the contractor or prospective contractor shall submit cost and pricing data. The contractor or prospective contractor shall certify that, to the best of the contractor’s or prospective contractor’s knowledge and belief, the data submitted is accurate, complete, and current as of […]
The state may, at reasonable times, inspect the part of the plant or place of business of a contractor or subcontractor that is related to the performance of a contract awarded or to be awarded by an agency.
(a) The state may, at reasonable times and places, audit the books and records of a person who has submitted cost or pricing data under AS 36.30.400 to the extent that the books and records relate to the cost or pricing data. A person who receives a contract, change order, or contract modification for which […]
(a) The commissioner shall adopt regulations permitting the inclusion of clauses providing for adjustments in prices, time of performance, or other contract provisions as appropriate. (b) The commissioner shall adopt regulations permitting or requiring the inclusion in state contracts of clauses providing for appropriate remedies and covering the following subjects: (1) liquidated damages; (2) specified […]
The procurement officer or the head of a contracting agency may vary the clauses adopted under AS 36.30.430 for inclusion in a particular state contract if the (1) variations are supported by a written determination that states the circumstances justifying the variation; and (2) approval required by AS 36.30.340 is obtained.
A contract modification, change order, or contract price adjustment under a construction contract in excess of an amount established by regulation of the commissioner is subject to prior written certification by the fiscal officer of the agency responsible for funding the project or the contract, or other official responsible for monitoring and reporting upon the […]
The commissioner shall adopt regulations setting out cost principles that shall be used to determine the allowability of incurred costs for the purpose of reimbursing costs under contract provisions that provide for the reimbursement of costs. If a written determination is approved at a level above the procurement officer, the cost principles may be modified […]