Section 5360.

5360. After the contractor has fulfilled his contract to the satisfaction of the street superintendent, or the engineer if such power has been delegated to him, the superintendent or engineer, as the case may be, shall forthwith make an assessment to cover the sum due for the work performed and specified in the contract, including […]

Section 5360.2.

5360.2. The street superintendent in making an assessment shall deduct from the total costs and expenses of the work any contributions authorized to be paid pursuant to Chapter 2.5 (commencing at Section 5125) of Part 3. (Added by Stats. 1963, Ch. 416.)

Section 5360.3.

5360.3. In assessing land, credit may be given for dedications and for improvements constructed at private expense. (Amended by Stats. 1974, Ch. 739.)

Section 5361.

5361. The assessment shall briefly refer to the contract, the work contracted for and performed, and shall show the amount to be paid therefor, together with all incidental expenses, the amount of each assessment against each lot or portion of a lot, the number of each lot or portion or portions of a lot so […]

Section 5362.

5362. The assessment shall be filed with the clerk. The clerk shall give notice of the filing of the assessment and of a time to be therein fixed by the clerk when all persons interested in the work done or in the assessment will be heard by the legislative body. The notice shall be posted […]

Section 5363.

5363. Such notice shall also be given by mail. (Added by Stats. 1941, Ch. 79.)

Section 5364.

5364. Such notice shall designate the property within the assessment district belonging to the owner by street number, or some other description sufficient to enable the property owner to identify the property, include a statement of the amount proposed to be assessed against such property, and state the name and telephone number of a local […]

Section 5365.

5365. Reference shall be made in the notices required by this chapter to the resolution of intention and the date of its passage for a description of the work therein mentioned and no other description thereof shall be necessary. (Amended by Stats. 1961, Ch. 57.)

Section 5366.

5366. The owners, the contractor, or his assigns, and all other persons interested in any work done under this division, or in the assessment, feeling aggrieved by any act or determination of the superintendent of streets or engineer in relation thereto, or who claim that the work has not been performed according to the contract […]

Section 5367.

5367. Upon such appeal, the legislative body may remedy and correct any error or informality in the proceedings, and revise and correct any of the acts or determinations of the street superintendent or engineer relative to said work; may confirm, amend, alter, modify or correct the assessment or diagram in such manner as to it […]

Section 5368.

5368. All the decisions and determinations of the legislative body, upon notice and hearing as aforesaid, shall be final and conclusive upon all persons entitled to appeal to the legislative body, as to all errors, informalities, and irregularities which the legislative body might have avoided, or have remedied during the progress of the proceedings or […]

Section 5369.

5369. No assessment, warrant, or diagram, and no proceedings prior to the assessment, shall be held invalid by any court for any error, informality, or other defect in the same, where the resolution of intention of the legislative body to do the work, has been actually published as provided in this division. When no appeal […]

Section 5370.

5370. Whenever the resolution of intention declares that a contribution of labor or of labor and any portion of materials, supplies or equipment for the proposed work will be made by any local, State or National agency or authority, an assessment shall be made to cover the sum due for furnishing the materials, supplies or […]

Section 5371.

5371. To the assessment shall be attached a warrant, which shall be signed by the superintendent of streets, and countersigned by the mayor or the city clerk. The warrant shall be substantially in the following form: By virtue hereof, I (name of the superintendent of streets), of the City of ______, County of ______ (or […]

Section 5372.

5372. The warrant, diagram and assessment shall be recorded in the office of the superintendent of streets and in accordance with Section 5372.1 and may be recorded at any hour of the calendar day. Immediately thereafter the clerk shall record a notice of assessment, as provided for in Section 3114, whereupon, as provided in Section […]

Section 5372.1.

5372.1. No assessment or bond hereafter levied or issued shall become a lien and no person shall be deemed to have notice thereof until a certified copy of the assessment and the diagram attached thereto shall be recorded in the office of the county surveyor if the improvement district or any part thereof is in […]

Section 5372.5.

5372.5. Upon the confirmation of the assessment by the legislative body, the clerk shall furnish the superintendent of streets with a list containing each assessment or parcel number, as shown on said recorded assessment, and the name and address of the owner or owners of the real property represented by each such number, as shown […]

Section 5373.

5373. The lien, whether bonds issued to represent the assessment or otherwise, shall be subordinate to all fixed special assessment liens previously imposed upon the same property, but it shall have priority over all fixed special assessment liens which may thereafter be created against the property; and from and after the date of the recording […]

Section 5374.

5374. The lien of a reassessment and a refunding assessment shall have the same priority as the original assessment to which it relates. A supplemental assessment is a new assessment. (Added by Stats. 1963, Ch. 1465.)

Section 5374.1.

5374.1. The amount of any contribution for the cost and expenses of the work shall be paid by the city to the contractor, or his agent, or assigns, upon delivery of the warrant, assessment and diagram, or prior to said delivery, may be paid in installments, for work completed, during the progress of the work. […]